Value Stream Mapping

Value Stream Mapping is every step, value adding or not, that it takes to bring one product from raw material to the customer. A value stream map is a one page picture of that stream. It shows three things at once: how material flows, how information flows, and how long everything takes. It's often called V S M. You draw a current state map of how things work today, then a future state map of how they should work.

7:52 · Q-Bot · narrated, with worked example and a check-yourself question

In short

A value stream map is a one page picture of material flow, information flow and time, for one product family. Walk it and count it yourself. Takt time is time available divided by customer demand. Each pile divided by daily demand gives days of waiting, and the timeline adds up lead time and value added time. Then draw the future state, and turn every kaizen burst into an action with an owner.

Check yourself

Between two steps, you count seven hundred twenty parts waiting. Customer demand is three hundred sixty parts a day. About how much waiting time goes on the timeline for that pile? A: half a day. B: two days. C: three hundred sixty minutes. Or D: seven hundred twenty days.

Show the answer

The answer is B, two days. Divide the pile by daily demand: seven hundred twenty divided by three hundred sixty is two. A flips the division. C mixes up parts and minutes. And D forgets to divide by demand at all. That's value stream mapping. Questions? Ask Q-Bot right here in the Academy. And one for the road: why don't value stream maps ever get lost? Because they always walk the floor first!

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

A while back, Rosa stood at the coating oven at Brindlewood, looking at racks of welded Harbor chair frames. "A Harbor chair takes forty five minutes of real work," she said. "So why does it take five days to get one out the door?" Marcus grabbed a clipboard and a pencil. "Let's walk it, and draw it!"

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: value stream mapping. We'll learn what a value stream map is, the five parts of drawing one, and how to read its timeline. Then we'll map the Harbor chair, from cut tube to the truck, together!

What it is

So, what is a value stream? It's every step, value adding or not, that it takes to bring one product from raw material to the customer. A value stream map is a one page picture of that stream. It shows three things at once: how material flows, how information flows, and how long everything takes. It's often called V S M. You draw a current state map of how things work today, then a future state map of how they should work.

Why it matters

Why does it matter? Because most waste hides between the steps, not inside them. Each department can look busy and efficient, while the product sits and waits. A value stream map puts the whole flow on one page, so everyone sees the same picture: the piles, the waiting, the extra handling, the rework loops. At Brindlewood, every department thought it was doing fine. And a chair still took five days!

How it works: five parts

Now, how it works. Part one: pick one product family, and walk it. A product family is a group of products that go through the same steps. Then go to the floor and walk the flow yourself, from the shipping door back upstream, with a pencil. Count what you see, and time it. Bad: mapping everything the plant makes, from a conference room. Good: one family, walked and counted on the floor!

Part two: the boxes and the data. The customer goes in the top right corner, with demand: how many, how often. From that you get takt time: the time available, divided by customer demand. It's the pace the customer is buying at. Each process gets a box, and under it, a data box: cycle time, changeover time, uptime, number of people, number of shifts. Bad: guessed numbers from the standard. Good: numbers you timed and counted yourself!

Part three: inventory and arrows. Between the boxes, a warning triangle marks every pile of waiting parts, with the count. A striped arrow means push: a step makes parts whether the next step needs them or not. A supermarket, or a first in, first out lane, means pull. Then add information flow along the top: who sends orders and schedules, and to whom. Bad: only drawing the machines. Good: the piles, the arrows, and the paperwork!

Part four: the timeline, along the bottom. It's a ladder. The high steps are waiting time: each pile divided by daily demand gives days of waiting. The low steps are value added time, the work the customer pays for. Add the high steps and the low steps, and you get lead time. Then divide value added time by lead time. That's the value added ratio. It's almost always tiny, and that's the point!

Part five: the future state, and the plan. Look at the current map and ask: what is takt time? Where can we flow? Where we can't flow, where can we pull? Which one step gets the schedule? Mark each idea with a kaizen burst, a little starburst on the map. Then turn every burst into an action plan, with an owner and a date. Bad: a pretty map on the wall. Good: a map with an action plan, and a date to map again!

Worked example: the Harbor chair

Now, let's map Brindlewood's Harbor chair. Customers order eighteen hundred chairs a week: three hundred sixty a day. Two shifts give nine hundred working minutes a day. Nine hundred minutes times sixty, divided by three hundred sixty chairs, is a takt time of one hundred fifty seconds. Marcus walks it: cutting and bending, welding, powder coating, then assembly and packing. And he counts every pile.

Let's do the math. Three hundred sixty cut tube sets wait before welding: one day. Six hundred welded frames wait at the oven: six hundred divided by three hundred sixty, about one point seven days. Three hundred sixty coated frames wait for assembly: one day. Four hundred fifty finished chairs wait for the truck: one and a quarter days. That's about four point nine days of waiting, plus forty five minutes of real work. Lead time: about five days. Value added ratio: under one percent!

And the map showed why. Welding had a goal of two hundred ten frames a shift: one every one hundred twenty eight seconds, faster than the one hundred fifty second takt. Coating can only take one hundred eighty a shift. So thirty extra frames a shift were pushed into the pile at the oven. And at the top, production control sent a weekly schedule to every department, so each one built to its own plan, not to what the next step needed.

So here's the future state. Assembly is the one step that gets the schedule. Welding works at coating's pace, one hundred eighty a shift. Between them, Lou paints a first in, first out lane that holds ninety frames, no more. Earlier steps refill what's used, so the piles shrink to a hundred eighty, ninety, a hundred eighty and about two hundred fifty chairs. That's under two days of waiting. Lead time: about two days, and the value added ratio more than doubles, to about two point three percent!

Common mistakes

Common mistakes. One: mapping from the office instead of walking the floor. Two: trying to map every product at once, instead of one family. Three: leaving out the information flow. Four: making the map, and never building an action plan. And five: drawing a future state and never mapping again to check it.

Recap

Let's recap. A value stream map is a one page picture of material flow, information flow and time, for one product family. Walk it and count it yourself. Takt time is time available divided by customer demand. Each pile divided by daily demand gives days of waiting, and the timeline adds up lead time and value added time. Then draw the future state, and turn every kaizen burst into an action with an owner.

Check yourself

Now, check yourself. Between two steps, you count seven hundred twenty parts waiting. Customer demand is three hundred sixty parts a day. About how much waiting time goes on the timeline for that pile? A: half a day. B: two days. C: three hundred sixty minutes. Or D: seven hundred twenty days. Pause the video if you want to think about it.

The answer is B, two days. Divide the pile by daily demand: seven hundred twenty divided by three hundred sixty is two. A flips the division. C mixes up parts and minutes. And D forgets to divide by demand at all.

That's value stream mapping. Questions? Ask Q-Bot right here in the Academy. And one for the road: why don't value stream maps ever get lost? Because they always walk the floor first!

Independent study material; not affiliated with or endorsed by ASQ. Body of Knowledge codes identify where the topic appears in each certification's published outline.