Academy › Topic library › Stakeholders

Q-BOT ACADEMY · FREE VIDEO LESSON · 9 MIN

Stakeholders

Anyone who affects your project, is affected by it, or even just believes they're affected by it. Internal stakeholders are inside the organization: the sponsor, the people who do the work, the departments upstream and downstream. External stakeholders are outside: customers, suppliers, the community next door, and regulators.

8:58 · Q-Bot · narrated, with worked example and a check-yourself question

In short

A stakeholder is anyone who affects, is affected by, or believes they're affected by your project. The sponsor owns the project, and the process owner owns the process. Identify them wide, write down their impacts, place them on the power and interest grid, close the commitment gaps, and engage them with a plan. And listen!

Check yourself

On your project, the H R manager has a lot of power, but the project barely affects her day. Where does she go on the grid? A, manage closely. B, keep satisfied. C, keep informed. Or D, monitor.

Show the answer

The answer is B, keep satisfied. High power and low interest means she can stop the project, but she doesn't need every detail. Give her what she needs to say yes, like the overtime rules met and the schedule posted on time, and no surprises. And watch her: if the project starts to affect her more, she moves to manage closely!

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Friday huddle at Brindlewood Outdoor Furniture. A big garden center chain wants one thousand four hundred forty extra Harbor chairs before April. Rosa has a plan: starting next week, the whole plant works Saturdays, eight Saturdays in a row. A sign-up sheet goes on the wall. By Monday, it has eleven names. Rosa needs sixty. Lou says, Saturday is the only day I can service the oven. Ellen says, our powder runs out by the third Saturday. And from the back of the room: nobody asked us!

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: stakeholders. We'll cover what a stakeholder is, why they matter, how to analyze them in five steps, and how Rosa got her Saturdays back on track.

What it is

So, what is a stakeholder? Anyone who affects your project, is affected by it, or even just believes they're affected by it. Internal stakeholders are inside the organization: the sponsor, the people who do the work, the departments upstream and downstream. External stakeholders are outside: customers, suppliers, the community next door, and regulators.

Two stakeholders have special jobs. The sponsor owns the project: sets the goal, provides the resources, and clears the roadblocks. The process owner owns the process, every single day, before the project, during it, and long after the team goes home. On a project at Brindlewood, Rosa is often the sponsor, and the line lead, like Dwayne in assembly, is the process owner. Bring the process owner in early, because they're the one who has to live with the result!

Why it matters

Why does it matter? Projects rarely fail because of the math. They fail because of people who were surprised. Rosa's plan was fine on paper: eight Saturdays, one hundred eighty chairs each, one thousand four hundred forty chairs. But the people who had to make it happen found out last, and the sign-up sheet had eleven names out of sixty, about eighteen percent. A surprised stakeholder becomes a blocker. An involved stakeholder becomes a helper!

How it works: 5 steps

So how does it work? Step one: identify. Brainstorm every stakeholder, wide. Ask: who does the work? Who supplies it? Who receives the result? Who pays for it? Who has to approve it? And who lives next door? Bad: the sponsor, the team, done. Good: a list of ten, including the quiet ones, like the maintenance tech and the neighbors!

Step two: impact. For each stakeholder, write down what they gain and what they lose, in their own words. Some impacts are good, some are bad, and many are both. Bad: assume everyone wants what the sponsor wants. Good: the crews gain overtime pay, but they lose their weekends, and that's the part they care about!

Step three: the power and interest grid. Score each stakeholder from one to five on power, how much they can help or block the project, and on interest, how much the project affects them. Three or more counts as high. High power and high interest: manage closely. High power, low interest: keep satisfied. Low power, high interest: keep informed. Low on both: monitor. Bad: treat everyone the same. Good: put your effort where the grid says!

Step four: commitment. For each key stakeholder, mark where they are today and where the project needs them to be. The scale runs from opposed, to not committed, to let it happen, to help it happen, to make it happen. The gaps are your to-do list. Bad: we'll win them over later. Good: four gaps, four names, four actions, starting this week!

Step five: engage. Plan who hears what, how, and how often, and match it to the grid. Manage closely means talk with them, and build the plan with them. Keep informed means regular updates. And most important: listen, then change the plan when they're right. Bad: announce the plan at the huddle. Good: ask first, then announce a plan they helped build!

The same thinking works for the whole organization. When leaders set strategy, they weigh the needs of customers, employees, owners, suppliers, the community and regulators. Those needs often pull in different directions: lower prices, higher pay, bigger profits, fewer trucks on the street. Bad: serve one group and surprise the rest. Good: name them all, and balance them on purpose!

Worked example: the Saturdays

Now, the worked example. Rosa pauses the Saturday plan, and Marcus runs a stakeholder analysis with her. They list ten stakeholders and score each one, power first, then interest. Rosa, five and five. The garden center chain, five and four. The production crews, four and five. Lou, three and five. The powder supplier, three and two. H R, four and two. Finance, three and two. Hannah's customer service team, two and three. The neighbors on Mill Street, two and one. And homeowners who buy online, two and one.

Now place them on the grid. Manage closely: Rosa, the garden center chain, the crews and Lou. That's four. Keep satisfied: the powder supplier, H R and finance. Three. Keep informed: Hannah's team. One. And monitor: the neighbors and the homeowners. Two. Four, plus three, plus one, plus two, ten stakeholders, every one with a plan!

Next, commitment. The crews are opposed today, and the plan needs them at help it happen. Lou is opposed too. The powder supplier and H R are not committed yet. Four gaps, four actions. The crews: Rosa asks at every shift huddle, and they build a rotation where each person works four of the eight Saturdays. Lou: the line runs six to two thirty, so he keeps Saturday afternoons for the oven. The supplier: Ellen sends an eight-week powder forecast that same day. And H R checks the overtime rules and posts the schedule two weeks ahead.

Here's the math. About one hundred twenty people work in production, and each Saturday needs sixty. One hundred twenty people times four Saturdays is four hundred eighty shifts. Sixty a Saturday times eight Saturdays is also four hundred eighty. It fits! One hundred twelve people sign up for four Saturdays each, that's four hundred forty-eight shifts, and volunteers pick up the other thirty-two. All eight Saturdays are full, Lou services the oven every Saturday afternoon, and one thousand four hundred forty chairs ship before April!

Common mistakes

A few common mistakes. One: listing only the obvious stakeholders. Two: confusing the sponsor with the process owner. Three: telling people instead of asking them. Four: doing the analysis once and never updating it, because people move around the grid. And five: ignoring the low-power groups, until they turn into a complaint.

Recap

Let's recap. A stakeholder is anyone who affects, is affected by, or believes they're affected by your project. The sponsor owns the project, and the process owner owns the process. Identify them wide, write down their impacts, place them on the power and interest grid, close the commitment gaps, and engage them with a plan. And listen!

Check yourself

Now, check yourself. On your project, the H R manager has a lot of power, but the project barely affects her day. Where does she go on the grid? A, manage closely. B, keep satisfied. C, keep informed. Or D, monitor. Pause the video if you want to think about it.

The answer is B, keep satisfied. High power and low interest means she can stop the project, but she doesn't need every detail. Give her what she needs to say yes, like the overtime rules met and the schedule posted on time, and no surprises. And watch her: if the project starts to affect her more, she moves to manage closely!

Wrap-up

That's stakeholders. Questions? Ask Q-Bot right here in the Academy. And here's one for the road: why did the vampire skip the project kickoff? He heard it would be full of stakeholders!