Planning and Managing the Project

The project charter says why the project exists and what it must deliver. The project plan says how, who, when, and how much. Managing the project means working that plan, every week: tracking progress, reviewing it at checkpoints, keeping the records, and closing the project out properly at the end.

9:36 · Q-Bot · narrated, with worked example and a check-yourself question

In short

The plan says how, who, when and how much. The work breakdown structure turns the project into tasks with owners. Estimates and a Gantt chart put them on a calendar, and the critical path sets the finish date. Track the schedule and the money every week, review at tollgates, keep one project file and a communication plan, and close the project properly!

Check yourself

A task in your project has nine days of slack. It's going to run six days late. What happens to the project's finish date? A, it moves six days later. B, it doesn't move, because the delay fits inside the slack. C, it moves three days later. Or D, the whole project has to be planned again.

Show the answer

The answer is B. Slack is the time a task can slip without moving the finish date. Six days late fits inside nine days of slack, so the finish stays put, and the task still has three days of slack left. A is the trap: that would only be true on the critical path. But keep watching it. Three more days late, and it joins the critical path!

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Six weeks ago at Brindlewood Outdoor Furniture, Rosa approved a simple project: move packing from the far end of the building right next to assembly, joined by a short roller conveyor. Everyone said, about a month. Today Dwayne asks, so when does the conveyor arrive? Ellen looks up. What conveyor? I thought Lou ordered it. Lou shrugs. I thought Marcus did. Nobody ordered it. The project is already late, and it hasn't even started!

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: planning and managing the project. We'll cover what it is, why it matters, the tools one at a time, and how Brindlewood got the packing move back on track.

What it is

So, what is it? The project charter says why the project exists and what it must deliver. The project plan says how, who, when, and how much. Managing the project means working that plan, every week: tracking progress, reviewing it at checkpoints, keeping the records, and closing the project out properly at the end.

Why it matters

Why does it matter? Without a plan, jobs fall between people, the slow items get ordered late, and nobody knows the project is late until the deadline. At Brindlewood, every week of delay is another week of pushing carts of chairs three hundred feet to packing, about sixty trips a shift!

How it works: the tools

So how does it work? Tool one, the work breakdown structure, or W B S. Start with the whole project and break it into deliverables, then break each deliverable into tasks small enough to estimate and hand to one owner. Bad: one line that says, move packing. Good: a layout drawing, the conveyor, the electrical work, the move, the training and a pilot run, each one with a name next to it!

Tool two, estimates and the Gantt chart. Estimate each task, not the whole project. When a task is uncertain, use a three-point estimate: the optimistic time, the most likely time, and the pessimistic time. The expected time is the optimistic time, plus four times the most likely, plus the pessimistic, all divided by six. Then draw a Gantt chart: one bar per task on a calendar, and diamonds for milestones. Bad: about a month. Good: a bar for every task, with a start, a finish and an owner!

Tool three, the critical path. Decide which tasks must finish before others can start, then add up the time along each chain of tasks. The longest chain is the critical path. It sets the finish date, and any delay on it delays the whole project. The other chains have slack, also called float: time they can slip without moving the finish. Bad: rush everything. Good: guard the critical path, and use the slack to balance the work!

Tool four, tracking. Every week, compare the plan with what really happened, for the schedule and for the money. Which milestones were hit? What has been spent, against what the plan said by now? If the scope changes, write the change down and get the sponsor to approve it. Bad: it's going fine. Good: the conveyor ships two days late. It's on the critical path, so the finish moves two days!

Tool five, phase reviews, often called tollgates. At each big milestone, the team stops and shows the sponsor the results so far. The sponsor decides: go on, go back and fix something, or stop the project. Bad: the sponsor sees the project for the first time at the end. Good: a short review at every milestone, with the decision written down!

Tool six, documentation and the communication plan. Keep one project file: the charter, the plan, the weekly status, the change log, the decisions and the meeting notes. The communication plan says who needs to know what, how often, and how. Bad: the plan lives in one person's head. Good: one shared file, a one-page status for the sponsor every week, and an update at the shift huddle for the people on the floor!

Tool seven, closure. Check the results against the goal in the charter. Hand the new process to its owner, with updated standard work and a way to keep it in control. Hold a lessons learned session, file the records, and thank the team. Bad: the team just drifts away. Good: the process owner signs off, and the next project starts smarter!

Worked example: the packing move

Now, the worked example. Marcus restarts the packing move with a real plan, in working days. A: the layout drawing, Marcus, three days. B: order and deliver the conveyor, Ellen. The supplier says ten days at best, twelve most likely, and twenty at worst. Ten, plus four times twelve, plus twenty, is seventy-eight. Divided by six, that's thirteen days. C: the electrical work, Lou, four days. D: move the benches and install the conveyor, Lou and Dwayne, two days. E: train the packers, Priya, two days. And F: a pilot week, Dwayne, five days. The budget is thirty-six thousand dollars.

Next, the critical path. The conveyor and the electrical work both need the layout first, and the move needs both of them. The conveyor path: three, plus thirteen, plus two, plus two, plus five. Twenty-five days! The electrical path: three, plus four, plus two, plus two, plus five, sixteen days. So the electrical work has nine days of slack. Rosa's deadline is thirty days, five days to spare. And here's the lesson from the first try: Ellen orders the conveyor the very day the layout is approved!

On day twelve, two things go wrong. Lou gets pulled away to fix the coating oven burner, so the electrical work runs three days late. That's inside its nine days of slack, so the finish doesn't move. But the conveyor supplier says it will ship two days late. That task is on the critical path, so the finish moves from day twenty-five to day twenty-seven. Still three days inside the deadline. Money: the plan said twenty thousand dollars spent by now, and the real number is twenty-one thousand five hundred, seven and a half percent over, for extra electrical parts. At the tollgate, Rosa looks at both numbers and says: go!

The pilot week ends on day twenty-seven, three days early. Cart trips to packing drop from about sixty a shift to zero. The final cost is thirty-seven thousand two hundred dollars, about three percent over the budget. Then closure. Dwayne signs off as the process owner, and packing's standard work is updated. The lessons learned: order the slow items the day the design is approved, and get ship dates in writing. Rosa adds both to the checklist for the next project, and the team gets pizza!

Common mistakes

A few common mistakes. One: planning once and never updating the plan. Two: tasks with no owner. Three: one big guess for the whole project instead of an estimate for each task. Four: hiding bad news until the deadline. And five: skipping closure, so the next project repeats the same mistakes.

Recap

Let's recap. The plan says how, who, when and how much. The work breakdown structure turns the project into tasks with owners. Estimates and a Gantt chart put them on a calendar, and the critical path sets the finish date. Track the schedule and the money every week, review at tollgates, keep one project file and a communication plan, and close the project properly!

Check yourself

Now, check yourself. A task in your project has nine days of slack. It's going to run six days late. What happens to the project's finish date? A, it moves six days later. B, it doesn't move, because the delay fits inside the slack. C, it moves three days later. Or D, the whole project has to be planned again. Pause the video if you want to think about it.

The answer is B. Slack is the time a task can slip without moving the finish date. Six days late fits inside nine days of slack, so the finish stays put, and the task still has three days of slack left. A is the trap: that would only be true on the critical path. But keep watching it. Three more days late, and it joins the critical path!

Wrap-up

That's planning and managing the project. Questions? Ask Q-Bot right here in the Academy. And here's one for the road: why did the Gantt chart go to therapy? It had too many dependencies!