Academy › Topic library › Part Qualification, First Article and PPAP
Q-BOT ACADEMY · FREE VIDEO LESSON · 10 MIN
Part Qualification, First Article and PPAP
Part Qualification, First Article and PPAP is proof, before you buy in volume, that a supplier's process can make your part right, every time, at the rate you need. Not one good sample. A capable process. It isn't only for parts: a calibration lab, a test lab, or a software vendor gets qualified the same way.
In short
Review the drawing with the supplier: title block, views, tolerances, and G D and T. Classify the characteristics together, and find the C T Qs. Write a qualification plan with every proof and its sample size. Use pee-pap to prove good parts at production rate. And validate it all, certificates and readiness review included, before the first order.
Check yourself
A supplier ships a lot with a signed paper that says, this material meets all specification requirements. There are no test results on it. What is it? A, a certificate of analysis. B, a certificate of compliance. C, a part submission warrant. D, a first article report.
Show the answer
The answer is B, a certificate of compliance! It's a signed statement of conformance, with no data. A certificate of analysis would show the actual test results for that lot. And a part submission warrant belongs to the pee-pap package, not to every lot. That's part qualification, first article, and pee-pap. Questions? Ask Q-Bot right here in the Academy. Why did the glide pass its pull test so easily? It really knew how to hold on!
Where this topic is taught
This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.
Full lesson transcript
The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.
Intro
Brindlewood, receiving dock. A small box arrives from the new glide maker, Candidate A. Ten black glides, every one perfect. These are great! Let's order three hundred sixty thousand. Ellen smiles, and shakes her head. Those ten were made by hand, by the toolmaker, on a quiet afternoon. I want to see what the mold makes at full speed, on a Friday night.
Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: part qualification, first article, and pee-pap! We'll read the drawing together, agree on what matters, build a qualification plan, run the production part approval process, and check the results before the first real order.
What it is
So, what is part qualification? It's proof, before you buy in volume, that a supplier's process can make your part right, every time, at the rate you need. Not one good sample. A capable process. It isn't only for parts: a calibration lab, a test lab, or a software vendor gets qualified the same way.
Why it matters
Why does it matter? A sample shows what a supplier can make once. Production shows what they make every day. Remember the old glide mold, where one cavity cut slightly oversize, and glides started popping off customers' chairs? Twenty four calls in three weeks, a sort of six thousand glides, and free glides mailed out. Qualification finds that before the first truck, not after.
How it works
Now, how it works. Step one: a technical review of the drawing, with the supplier at the table. Check the title block: part number, revision, units, scale, and general tolerances. Check the views, so everyone sees the same shape. Then the dimensions and tolerances, and the G D and T symbols: a flatness box on the base, a perpendicularity box on the stem, each tied to a datum. Bad: the supplier quotes from an old revision. Good: everyone signs off on the same revision, line by line!
Step two: work with the supplier to define and classify the quality characteristics. Which ones are critical, major, or minor? Which are the C T Qs, the critical to quality ones the customer would feel? Those special characteristics get the tightest controls, and they're marked on the drawing and in the control plan. Bad: every dimension treated the same. Good: both sides agree which few really matter!
Step three: write the qualification plan together. It lists what will be proven, and how. An audit of the supplier's process. Calibration of every gauge used. Sample sizes. A first article inspection. Measurement system analysis. A process flow diagram, an F M E A, and a control plan. Capability studies on the C T Qs. Material and performance tests, appearance approval, and finally your own internal validation. Bad: we'll check some parts when they come. Good: every proof, its sample size and its owner, written down first!
Inside that plan, the first article inspection deserves a closer look. Take the first parts off the real production tooling, and measure every characteristic on the drawing. Every single one, with each one numbered on a ballooned drawing. A multi-cavity mold? One from every cavity. The report shows each number, the requirement, and the measured result. Bad: measure the three easy ones. Good: every balloon, every cavity!
Step four: production part approval, or pee-pap. It asks one big question. Can the supplier make good parts during a real production run, at production rate, with the real tooling, people, gauges and materials? The supplier assembles a package of up to eighteen elements: design records, the flow diagram, F M E A, control plan, M S A, dimensional results, material and performance tests, capability studies, the appearance report, sample parts, and a part submission warrant that signs it all off.
How much do they send? That's the submission level. Level one: just the warrant. Level three, the usual default: the warrant, sample parts, and all the supporting data. Level five: everything, reviewed at the supplier's plant. The customer picks the level, based on risk. Bad: the supplier decides what to send. Good: the customer sets the level, and the supplier knows it up front!
Step five: validate the requirements. Your internal team reviews the results of the whole plan. Watch the paperwork. A certificate of compliance, or C of C, is the supplier's signed statement that the lot meets the requirements. A certificate of analysis, or C of A, goes further: it reports actual test results for that lot. Then a production readiness review checks capacity, packaging, labels, training and gauges. The result: approved, interim approval, or rejected.
Worked example: the new glide
Let's work it at Brindlewood. Ellen and Marcus sit down with Candidate A over the glide drawing. Height: twelve millimeters, plus or minus point three. Stem: twenty two point four, plus or minus point one, so it grips the twenty two millimeter leg tube. Base flatness: point two. In the title block, Marcus spots it right away! Candidate A quoted from revision A. Revision B made the stem wider. Fixed before any steel is cut.
Next, they classify. Pull-off force, at least thirty pounds, and height are major: the customer feels them as a loose glide or a wobbly chair. Color and marks on a patio are minor. The plan: one first article from each of the four cavities, eight characteristics each, thirty two measurements. Thirty glides per cavity for capability on height. Thirty pull tests. A rub test on a patio tile. Priya checks her height gauge first: calibrated, and a gauge study shows it's good enough for this tolerance.
Then the run at rate. Candidate A runs the new four cavity mold for two hours, on a thirty second cycle. That's two hundred forty shots, times four cavities: nine hundred sixty glides, or four hundred eighty an hour. Brindlewood needs three hundred sixty thousand a year, about seven thousand two hundred a week. On one shift, five days, the mold can make nineteen thousand two hundred. Brindlewood needs about thirty eight percent of that. Plenty of room!
Now the height capability, from thirty glides per cavity. The run looked stable, so Priya works out P P K: the distance from the average to the nearest limit, divided by three standard deviations. Cavity one: point two eight, over point one two. Two point three three. Cavities two and four: two point oh seven, and two point five four. Cavity three averages twelve point one. Only point two to the upper limit, over point one two six: one point five nine. A new process is usually asked to show one point six seven. Cavity three again!
Candidate A adjusts the steel in cavity three, and reruns it. New average: twelve point oh one, P P K two point three six. All thirty pull tests hold above forty pounds. No marks on the patio tile. The resin comes with a C of A showing the lot's real test results, not just a C of C. At the production readiness review, packaging and labels check out. Ellen signs. Approved!
Common mistakes
Common mistakes. Approving from hand-picked samples. Building to an old revision. Measuring one cavity and assuming the rest match. Using a gauge nobody checked. Accepting a C of C when you needed real test results. And skipping the run at rate.
Recap
Let's recap. Review the drawing with the supplier: title block, views, tolerances, and G D and T. Classify the characteristics together, and find the C T Qs. Write a qualification plan with every proof and its sample size. Use pee-pap to prove good parts at production rate. And validate it all, certificates and readiness review included, before the first order.
Check yourself
Check yourself. A supplier ships a lot with a signed paper that says, this material meets all specification requirements. There are no test results on it. What is it? A, a certificate of analysis. B, a certificate of compliance. C, a part submission warrant. D, a first article report. Pause the video if you want to think about it.
The answer is B, a certificate of compliance! It's a signed statement of conformance, with no data. A certificate of analysis would show the actual test results for that lot. And a part submission warrant belongs to the pee-pap package, not to every lot.
That's part qualification, first article, and pee-pap. Questions? Ask Q-Bot right here in the Academy. Why did the glide pass its pull test so easily? It really knew how to hold on!