Lean: Value and the Eight Wastes
Lean is a way of running any process, on a floor or in an office, that gives the customer what they value with as little waste as possible. It starts with one word: value. Value is what the customer is willing to pay for. A Brindlewood customer pays for a sturdy, good-looking chair that doesn't wobble. They don't pay for it to sit on a rack, or to ride a forklift around the building.
In short
Value is what the customer is willing to pay for. Every step is value added, necessary but not value added, or pure waste. The five principles are value, value stream, flow, pull and perfection. The eight wastes spell DOWNTIME. And the biggest gains come from removing the waste around the work, not from rushing the work.
Check yourself
At Brindlewood, welders walk sixty feet to a shared cabinet every time they need a new welding tip. Which waste is that? A, transportation. B, motion. C, waiting. Or D, overproduction.
Show the answer
The answer is B, motion. The person is moving, not the product. If the tips were being trucked around the building, that would be transportation. The fix: keep a few tips at each welding station.
Where this topic is taught
This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.
Full lesson transcript
The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.
Intro
It's Monday morning at Brindlewood Outdoor Furniture. Rosa, the plant manager, follows one Harbor chair through the building, from a stick of aluminum tube to a packed box. She times every minute someone actually works on it: forty five minutes. Then she checks how long the chair spent inside the plant. Five whole days! Where did the rest of the time go?
Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: Lean, value and the eight wastes. We'll define value, walk through the five Lean principles, meet all eight wastes, and do the math on Rosa's chair.
What it is
So, what is Lean? Lean is a way of running any process, on a floor or in an office, that gives the customer what they value with as little waste as possible. It starts with one word: value. Value is what the customer is willing to pay for. A Brindlewood customer pays for a sturdy, good-looking chair that doesn't wobble. They don't pay for it to sit on a rack, or to ride a forklift around the building.
That sorts every step into three kinds. One, value added: the step changes the product into what the customer wants, done right the first time, like bending and welding the frame. Two, necessary but not value added: the customer doesn't pay for it, but we can't skip it today, like the weld pull test. Keep it, and make it lean. Three, pure waste: everything else. Remove it.
Why it matters
Why does this matter? Because waste is expensive, and it hides in plain sight. Every chair on a rack is money sitting still. Every extra trip, every rework, every hour of waiting adds cost and time, and the customer gets nothing for it. Here's the big idea: most improvement doesn't come from speeding up the value added work. It comes from removing the waste around it!
How it works: the five principles
Lean has five principles. One, value: define it from the customer's point of view. Two, the value stream: every step the product goes through, from raw material to the customer. Three, flow: keep the product moving through those steps without stopping. Four, pull: make only what the customer has ordered, when they need it. And five, perfection: keep repeating the cycle, because there's always more waste to find. Flow, pull and value stream maps get their own videos. Today, we focus on waste.
The eight wastes (DOWNTIME)
Lean names eight wastes, and they spell the word DOWNTIME. D is for defects: anything made wrong that gets scrapped, reworked or sent back. Brindlewood's top complaint is the wobbly chair, from legs cut to different lengths. Bad: add another inspector at the end of the line to catch them. Good: fix the cut, so every leg comes out the same length.
O is for overproduction: making more, or sooner, than the customer needs. It's often called the worst waste, because it creates most of the others. Bad: running four hundred Ridge benches because the setup is already done, when there are orders for two hundred fifty. Good: building to the orders, and working on faster setups so smaller runs make sense.
W is for waiting: people or machines idle, because the next part, tool, approval or piece of information isn't there yet. Bad: a welder standing at an empty fixture for twenty minutes, waiting for bent frames. Good: balance bending and welding, so frames arrive at a steady pace.
N is for non-utilized talent: not using people's skills and ideas. The people who do the work usually know exactly where the waste is. Bad: Dwayne's assembly crew is told, just build chairs, the engineers handle improvement. Good: the crew gets ten minutes each shift to point out problems, and their ideas get tried.
T is for transportation: moving materials, parts or paperwork more than needed. Moving a part never makes it better, and every move risks a dent. Bad: welded frames go to a storage area at the far end of the building, then come back to the coating line. Good: frames go straight from welding to coating.
I is for inventory: more material, work in progress or finished goods than the next step needs. It ties up cash and space, and it hides problems: a defect may not show up until hundreds of bad parts are made. Bad: six hundred frames stacked on racks in front of the coating oven. Good: a small, marked space in front of the oven that holds only what the next hour needs.
M is for motion: people moving more than the work needs, like walking, reaching or searching. Transportation moves the product. Motion moves the person. Bad: at assembly, the bolt bin is thirty feet from the bench. Twenty five round trips a shift is fifteen hundred feet of walking. Good: the bolts sit at the bench, within arm's reach.
And E is for extra processing: doing more than the customer values, or more than the spec asks for. Bad: sanding the underside of every slat to a showroom finish no customer will ever see. Good: finish to the customer's requirement, and stop there. That's DOWNTIME!
Worked example: the Harbor chair
Now let's do the math on Rosa's chair. She added up the value added steps. Cutting and bending: four minutes. Welding: nine minutes. Powder coating in the oven: twenty minutes. Slat fitting and assembly: twelve minutes. Four plus nine plus twenty plus twelve is forty five minutes of value added time.
The lead time, the total time in the plant, was five days. With two eight hour shifts, that's eighty working hours, or four thousand eight hundred minutes. The value added ratio is value added time divided by lead time: forty five divided by four thousand eight hundred, about zero point nine percent. For over ninety nine percent of its time in the plant, the chair was just waiting or moving!
Marcus and the team went after the waste, not the welders. They cut the trip to the far storage area, shrank the pile of frames at the oven, and moved the bolts to the benches. Lead time dropped to two days: thirty two working hours, or one thousand nine hundred twenty minutes. The value added time stayed at forty five minutes, so the ratio rose to about two point three percent, and customers got their chairs three days sooner. Nobody had to work faster!
Common mistakes
A few common mistakes. One: defining value from the inside, instead of asking what the customer will pay for. Two: treating Lean as cutting people. Lean cuts waste, and it needs the people who do the work to find it. Three: removing a necessary step, like a required test, just because it isn't value added. Make it leaner instead. And four: fixing one waste and calling it done. Perfection means keep looking.
Recap
Let's recap. Value is what the customer is willing to pay for. Every step is value added, necessary but not value added, or pure waste. The five principles are value, value stream, flow, pull and perfection. The eight wastes spell DOWNTIME. And the biggest gains come from removing the waste around the work, not from rushing the work.
Check yourself
Now, check yourself. At Brindlewood, welders walk sixty feet to a shared cabinet every time they need a new welding tip. Which waste is that? A, transportation. B, motion. C, waiting. Or D, overproduction. Pause the video if you want to think about it.
The answer is B, motion. The person is moving, not the product. If the tips were being trucked around the building, that would be transportation. The fix: keep a few tips at each welding station.
Wrap-up
That's Lean, value and the eight wastes. Questions? Ask Q-Bot right here in the Academy. And here's one for the road: why did the forklift go to therapy? It had too much baggage, and it kept moving it around for no reason!