Lean Flow in Depth: Flow Metrics, Little's Law, SMED and Heijunka

Flow is how smoothly work moves from the first step to the customer, without waiting. And you can't improve flow by feel. You measure it. Six numbers do most of the work: work in process, work in queue, touch time, cycle time, throughput and takt time. Put them together and they point straight at the constraint, the one step that holds the whole process back.

9:14 · Q-Bot · narrated, with worked example and a check-yourself question

In short

Measure flow with work in process, work in queue, touch time, cycle time, throughput and takt. Little's Law: lead time equals work in process divided by throughput. The hidden factory hides rework and eats capacity. Smed: separate, convert, streamline. Hay-joon-kah levels volume and mix, and works best with continuous flow and pull. The same tools work at your suppliers, too.

Check yourself

A process holds six hundred units in process and finishes two hundred units a day. About how long is the lead time? A, three days. B, one third of a day. C, eight hundred days. D, one hundred twenty thousand days.

Show the answer

The answer is A, three days! Lead time equals work in process divided by throughput. Six hundred divided by two hundred is three. Picked B? You flipped the fraction. Throughput goes on the bottom. That's lean flow in depth: flow metrics, Little's Law, Smed and hay-joon-kah. Questions? Ask Q-Bot right here in the Academy. Why did the slat set refuse to wait in the pile? It wanted to go with the flow!

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Brindlewood, Monday morning. Ellen hangs up the phone and sighs. The slat supplier is late again! Only fifteen of the last twenty deliveries came on time and in full, and a new slat order now takes four weeks. Dwayne's line almost ran out of Ridge bench slats on Friday. Ellen asks the supplier's owner, Nell, what's wrong. Nell says her machines are running flat out. Marcus grabs his clipboard. If the machines are flat out, where are four weeks going? Let's go count.

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: lean flow in depth! We'll measure flow with a handful of numbers, use Little's Law to see where the time goes, find the hidden factory, cut a changeover with Smed, and level the work with hay-joon-kah.

What it is

So, what is flow? Flow is how smoothly work moves from the first step to the customer, without waiting. And you can't improve flow by feel. You measure it. Six numbers do most of the work: work in process, work in queue, touch time, cycle time, throughput and takt time. Put them together and they point straight at the constraint, the one step that holds the whole process back.

Why it matters

Why does it matter? When orders are late, the first idea is usually to run the machines faster, or buy another machine. But most of the time, a part isn't being worked on at all. It's sitting in a pile, waiting. Speed up a machine and the parts still wait. Shrink the piles, and the same machines deliver in days instead of weeks!

How it works

Now, how it works. Component one: the flow metrics. Work in process, or W I P, is every unit that has started but not finished. Work in queue is the part of it that's just waiting in line, not on a machine. Touch time is the time someone or something actually works on one unit. Bad: counting only the parts on the machines. Good: walk the whole process and count every pile, every cart, every rack!

Cycle time is how often a finished unit comes off a step, like one slat set every sixty seconds. Throughput is how many units leave the whole process in a day. Takt time is the customer's pace: available working time divided by customer demand. Any step with a cycle time longer than takt can't keep up. That step is the constraint. Bad: a machine's catalog speed. Good: a stopwatch, on the floor, on a normal day!

Component two: Little's Law. Lead time equals work in process divided by throughput. If a process holds six hundred units and finishes two hundred a day, a new unit waits about three days to get out. Two rules. Use the same units, like sets and sets per day. And use long-run averages from a fairly steady process, not one crazy afternoon.

Component three: the hidden factory. That's all the work nobody planned and nobody reports: rework, re-inspection, parts walking back to an earlier step. It eats capacity, adds work in process, and stretches lead time, but it never shows up on the schedule. Bad: the report says the machine takes sixty seconds. Good: follow ten units, and count every trip through every step!

Component four: Smed, single minute exchange of die. It cuts changeover time, so you can switch products often and run small batches. Three steps. One, separate the external work, which can be done while the machine runs, from the internal work, which can only be done while it's stopped. Two, convert internal work to external. Three, streamline whatever is left. Bad: hunting for tools while the machine sits. Good: everything ready on a cart before you stop!

Component five: hay-joon-kah, which means leveling. Instead of making all of one product, then all of the next, you level both the volume and the mix, so every day looks about the same. That only works once changeovers are short. Add continuous flow, small lots moving straight to the next step through first in, first out lanes, and pull, so you only make what the customer used. Bad: one big batch per product per week. Good: a little of every product, every day!

Worked example: the slat supplier

Let's work it at the slat supplier. Ellen, Marcus and Nell walk the line: rip saw, planer, sander and packing, one shift, four hundred fifty minutes a day, five days a week. Brindlewood needs eighteen hundred Harbor chair slat sets and one hundred twenty Ridge bench sets a week. That's nineteen hundred twenty sets. Two thousand two hundred fifty minutes divided by nineteen hundred twenty sets is a takt time of about seventy seconds a set.

Now they count every pile. Three thousand eight hundred forty sets cut and waiting for the planer. Nineteen hundred twenty planed, waiting for the sander. Nine hundred sixty sanded, waiting to pack. Nine hundred sixty packed, waiting for the truck. Seven thousand six hundred eighty sets in process, and only about ten of them on a machine. Throughput is three hundred eighty four sets a day. Little's Law: seven thousand six hundred eighty, divided by three hundred eighty four. Twenty days! There's the four weeks.

And the touch time? Thirty seconds on the rip saw, forty eight on the planer, sixty on the sander and eighteen to pack. Two point six minutes of work, inside twenty days of waiting! Then Marcus follows ten sets and finds the hidden factory. About fifteen percent go back through the sander for a second pass, on no report at all. So the sander really takes about sixty nine seconds per good set, against a takt of seventy. Barely one second to spare. That's the constraint.

Why such big piles? The planer takes a hundred twenty minutes to change from Harbor slats to Ridge slats, so Nell runs a whole week of one, then the other. Switching every day would need two changeovers, two hundred forty minutes, plus about three hundred seven minutes of planing. Five hundred forty seven minutes. More than the four hundred fifty in a shift! So they film a changeover. Forty minutes is external: finding the fence, the setup sheet and a forklift. Off the clock. Eighty minutes left.

Next, they convert. A second fence gets set up on a bench while the planer runs. Thirty more minutes gone. Fifty left. Then they streamline: hand knobs instead of six bolts, and a setup block instead of three trial boards. The changeover drops from a hundred twenty minutes to nine! Now two changeovers a day take eighteen minutes, and the day fits in about three hundred twenty five.

Now the plan. Hay-joon-kah: every day, three hundred sixty Harbor sets and twenty four Ridge sets. Small carts move through first in, first out lanes. Brindlewood's empty carts come back as kanban signals, so Nell makes what was used. The sander gets a fresh belt on a count, and re-sands drop to about two percent. Work in process falls to eleven hundred fifty two sets. Little's Law: three days! The next twenty deliveries? Twenty on time and in full.

Common mistakes

Common mistakes. Speeding up a machine that isn't the constraint. Mixing units in Little's Law, like sets in process and chairs per week. Trusting the report and missing the hidden factory. Leveling the schedule before the changeovers are short. And at a supplier: demanding faster delivery without helping them see their own flow.

Recap

Let's recap. Measure flow with work in process, work in queue, touch time, cycle time, throughput and takt. Little's Law: lead time equals work in process divided by throughput. The hidden factory hides rework and eats capacity. Smed: separate, convert, streamline. Hay-joon-kah levels volume and mix, and works best with continuous flow and pull. The same tools work at your suppliers, too.

Check yourself

Check yourself. A process holds six hundred units in process and finishes two hundred units a day. About how long is the lead time? A, three days. B, one third of a day. C, eight hundred days. D, one hundred twenty thousand days. Pause the video if you want to think about it.

The answer is A, three days! Lead time equals work in process divided by throughput. Six hundred divided by two hundred is three. Picked B? You flipped the fraction. Throughput goes on the bottom.

That's lean flow in depth: flow metrics, Little's Law, Smed and hay-joon-kah. Questions? Ask Q-Bot right here in the Academy. Why did the slat set refuse to wait in the pile? It wanted to go with the flow!