Inspection Types and Inspection Points is comparing a product to its requirements, and deciding: does it conform, or not? You measure, look or test, then compare to the drawing or the spec. An inspection type is when and where that check happens in the flow. An inspection point is the exact spot in the process where you stop and check. Inspection doesn't add value by itself. It catches problems. So the question is always the same: where is the cheapest place to catch this one?

8:34 · Q-Bot · narrated, with worked example and a check-yourself question

In short

Inspection compares the product to its requirements. Receiving and source inspection check what suppliers send. First article proves a new part; first piece proves every setup. In-process checks happen where the feature is made: self, patrol or station. Final inspection is the backstop. And put your inspection points before costly, permanent or hidden steps, and after every change.

Check yourself

A die change on a press just finished, and the next run is five hundred parts. Which inspection belongs right here, before the run? A: receiving inspection. B: first piece inspection. C: final inspection. Or D: source inspection.

Show the answer

The answer is B, first piece inspection. A setup just changed, so check the first part before the other four hundred ninety nine get made. A is for material arriving from a supplier. C comes at the end, after all five hundred are made. And D happens at the supplier's plant, not on your press.

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Monday afternoon at Brindlewood. Dwayne's line can't get the back slats to line up on a whole cart of Harbor chair frames. Priya checks the back legs. They're bent at one oh two degrees. The drawing says one oh five, plus or minus one! Sixty frames, already bent, welded and coated. And every check along the way looked at something else.

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: inspection types and inspection points. We'll walk the five places a part gets checked, from the supplier's dock to the shipping door, and how to choose where your checks belong. Then we'll map Brindlewood's Harbor chair together!

What it is

So, what is inspection? It's comparing a product to its requirements, and deciding: does it conform, or not? You measure, look or test, then compare to the drawing or the spec. An inspection type is when and where that check happens in the flow. An inspection point is the exact spot in the process where you stop and check. Inspection doesn't add value by itself. It catches problems. So the question is always the same: where is the cheapest place to catch this one?

Why it matters

Why does it matter? Because a defect gets more expensive every step it travels. A back leg bent wrong, caught at the bender, costs about six dollars: one tube. After welding, that frame is about twenty eight dollars of work. After coating, add eighteen more: forty six dollars. At the customer, it's a whole new chair plus freight, and a customer who remembers. Monday's sixty frames cost two thousand seven hundred sixty dollars!

How it works: five inspection types

Now, how it works. Part one: receiving inspection, also called incoming inspection. Material from suppliers is checked when it arrives, before anyone uses it. That might mean reading the supplier's certificate, checking a sample, or both. Its cousin is source inspection: checking at the supplier's plant, before the truck is loaded. It fits parts that are critical, costly, or hard to check once they arrive. Bad: unloading lots straight into production. Good: a hold lane, a check, and a green tag before anyone uses it!

Part two: first article and first piece inspection. A first article inspection is a full check of every drawing requirement on the first part made from a new design, a new supplier, or a changed drawing. It proves the process can make the part. A first piece inspection is smaller and happens much more often: the first part after every setup, die change or shift start, checked before the run goes on. Bad: start the run, and check later. Good: check piece one, then run!

Part three: in-process inspection, the checks during production. There are three common ways. Operator self-inspection: the person who makes it checks it, right away. Patrol inspection, also called roving: an inspector walks the line and checks samples at each station. And a fixed inspection station, where parts come to the check. A successive check is a cousin: the next operator checks the step before. Bad: waiting for the end of the line to find out. Good: check where the feature is made, while you can still fix the process!

Part four: final inspection, the last check before the product goes to the customer. It looks at the finished product the way the customer will see it and use it. It's the last chance, so it matters, but it's also the most expensive place to find a problem. Everything has already been spent. Bad: final inspection as the only real check. Good: final inspection as a backstop, confirming what earlier checks already controlled!

Part five: choosing inspection points, and how much to check. Put a check before an expensive step, before a step you can't undo, before a feature gets hidden, and right after a setup or a change. Then decide how much. One hundred percent inspection fits critical, quick checks, but people miss things: in Brindlewood's rocking study, one packer agreed with the measured answer only eighty percent of the time. Sampling fits big lots and any test that destroys the part. Bad: more checks everywhere. Good: the right check, at the right point!

Worked example: the Harbor chair

Now, let's map Brindlewood's Harbor chair. Marcus and Priya walk the flow with a clipboard. Receiving: fifty slats per lot, two from each bundle, and one glide per mold cavity pull tested. Welding: a weld counter on each fixture, and Priya pull tests one frame per station every shift. Coating: ten frames a shift on the control chart. Assembly: the self check. And final: coating and the rocking check on every chair. Lots of checks. But look between cutting and welding.

There's nothing there! Friday on second shift, the bender changed from Ridge bench tubes back to Harbor chair legs. The angle stop was left three degrees short. Nobody checked the first bent leg. Welding's checks look at welds. Coating's checks look at powder. Neither one measures a bend angle. So sixty frames rode right past three checks, until Dwayne's slats wouldn't fit.

Let's do the math. Each frame was bent, welded and coated: twenty eight dollars, plus eighteen for coating, is forty six dollars a frame. Sixty frames times forty six is two thousand seven hundred sixty dollars, plus an afternoon on Dwayne's line. Now picture a first piece check at the bender. The first leg is measured, it reads one oh two, and the stop gets fixed. Cost: one six dollar tube, and about two minutes!

So here's the fix. Lou and Marcus add a first piece check at the bender: after every die change and every shift start, the operator bends one leg, checks it with the angle gauge from the bender's shadow board, and initials the setup sheet. Leg in spec, then run. And Priya adds the bend angle to her patrol check once a shift. Over the next four weeks, twenty two die changes, two stops caught on the first leg, and zero bent frames reached assembly!

Common mistakes

Common mistakes. One: counting on final inspection to catch everything. Two: skipping the first piece check because the last run was fine. Three: checks that look busy but never measure the feature that fails. Four: trusting one hundred percent visual inspection to be one hundred percent effective. And five: adding checks everywhere, instead of fixing the process that needs them.

Recap

Let's recap. Inspection compares the product to its requirements. Receiving and source inspection check what suppliers send. First article proves a new part; first piece proves every setup. In-process checks happen where the feature is made: self, patrol or station. Final inspection is the backstop. And put your inspection points before costly, permanent or hidden steps, and after every change.

Check yourself

Now, check yourself. A die change on a press just finished, and the next run is five hundred parts. Which inspection belongs right here, before the run? A: receiving inspection. B: first piece inspection. C: final inspection. Or D: source inspection. Pause the video if you want to think about it.

The answer is B, first piece inspection. A setup just changed, so check the first part before the other four hundred ninety nine get made. A is for material arriving from a supplier. C comes at the end, after all five hundred are made. And D happens at the supplier's plant, not on your press.

Wrap-up

That's inspection types and inspection points. Questions? Ask Q-Bot right here in the Academy. And one for the road: why did the first piece get so much attention? Because everyone knows you only get one chance to make a first impression!