Going Deeper: Individuals and Moving Range Charts

When the test destroys the part, like a weld pull. When the process is slow, like one batch or one lot a day. When one reading tells the whole story, like the oven temperature each morning, or the gloss of each powder lot. And for monthly numbers, like scrap cost. There's no subgroup, so there's no range inside a subgroup. So we borrow the short-term variation from the next best place: the change from one reading to the next.

11:58 · Q-Bot · narrated, with worked example and a check-yourself question

In short

Use an I M R chart when you get one reading at a time. Moving range: the difference between neighbors. I chart: X bar, plus or minus two point six six M R bar. Moving range chart: upper limit three point two six seven M R bar. Sigma hat is M R bar over one point one two eight, never the overall standard deviation. Check for skew and for readings that follow each other. And a point outside the control limits is a signal, even when it's in spec!

Check yourself

Ellen charts moisture in the slat supplier's lumber, one reading per lot. The average is nine point oh percent, and M R bar is point six. What is the upper control limit on the I chart? A, ten point eight. B, ten point six. C, eleven point oh. Or D, nine point six.

Show the answer

The answer is B, ten point six. Two point six six times point six is about one point six. Add it to nine point oh, and you get about ten point six percent. A used three times M R bar, and skipped dividing by d two. C used three point two six seven, which belongs on the moving range chart. And D just added M R bar. That's individuals and moving range charts. Questions? Ask Q-Bot right here in the Academy. And one for the road: why did the individuals chart never join a subgroup? It liked to keep its distance, one reading at a time!

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Brindlewood, the welding bay. Every shift, Priya pulls one Harbor chair frame from welding station three and tears its weld apart on the pull tester. One frame, because the test destroys it. Marcus wants the results on a control chart. Dwayne laughs. An X bar chart needs five parts a subgroup. You'd be pulling apart five chairs a shift! And Ellen has the same puzzle: one gloss reading for every powder lot. One number at a time. So how do you chart that?

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today we're going deeper: individuals and moving range charts! We'll see when one reading at a time is the right choice, work every formula, build a chart for weld pull strength, see why the overall standard deviation gives the wrong limits, and finish with the cautions this chart needs. If control charts are new to you, start with the control charts for variables data video.

When one reading at a time?

When do you get only one reading at a time? When the test destroys the part, like a weld pull. When the process is slow, like one batch or one lot a day. When one reading tells the whole story, like the oven temperature each morning, or the gloss of each powder lot. And for monthly numbers, like scrap cost. There's no subgroup, so there's no range inside a subgroup. So we borrow the short-term variation from the next best place: the change from one reading to the next.

The I-MR formulas

Here are the formulas. The moving range is the absolute difference between each reading and the one before it. Twenty readings give nineteen moving ranges. M R bar is their average. The individuals chart, or I chart, has a center line at X bar, the average of the readings. Its limits are X bar, plus or minus two point six six times M R bar. The moving range chart has a center line at M R bar, an upper limit of three point two six seven times M R bar, and a lower limit of zero.

Where do two point six six and three point two six seven come from? A moving range is the range of a subgroup of two: this reading and the last one. So we use the constants for n equals two from the control chart constants table. d two is one point one two eight, so sigma hat equals M R bar divided by one point one two eight. Three divided by one point one two eight is two point six six. And D four for n equals two is three point two six seven. In a spreadsheet, each moving range is ABS of this cell minus the cell above.

Worked example 1: station 3 pull test

Worked example one: station three's weld pull test. The minimum is twelve hundred pounds. Over twenty shifts, Priya's readings start at fifteen fifteen, fourteen seventy, fourteen ten, and fourteen thirty. The first moving range is fifteen fifteen minus fourteen seventy: forty five. Then sixty. Then twenty. The twenty readings average exactly fourteen fifty pounds. And the nineteen moving ranges add up to seven hundred sixty, so M R bar is forty.

Just like the range chart, check the moving range chart first. Its upper limit is three point two six seven times forty: about one hundred thirty one pounds. The largest moving range is ninety. All nineteen are inside. The short-term variation is steady, so we can trust it to build the I chart.

Now the I chart. Two point six six times forty is one hundred six point four. So the limits run from thirteen forty three point six to fifteen fifty six point four pounds. Every reading sits between thirteen eighty five and fifteen twenty. In control! Sigma hat is forty divided by one point one two eight: about thirty five pounds. And look where the lower limit sits: about one hundred forty pounds above the twelve hundred minimum. So the chart can warn us long before a weld fails the spec.

Marcus freezes the limits, and the chart goes up by the welding bay. Seven shifts into phase two, the pull reads thirteen ten pounds. That's still above twelve hundred, so the weld passes the spec. But it's below the thirteen forty three point six control limit. Something changed! The moving range is fourteen forty five minus thirteen ten: one hundred thirty five, above its limit too. Priya doesn't wait for a weld to fail.

Lou finds it fast. At the shift change, a gas cylinder from the maintenance shop was hooked to station three. It's a mix made for steel. Aluminum needs pure argon. Lou swaps the cylinder and tags every cylinder by type, and the steel mix stays in the shop. Rosa holds that shift's frames from station three, and five more pulls all read well above twelve hundred, so they're released. The next shift reads fourteen fifty five. Notice the moving range chart: one hundred forty five, a second spike! One odd reading makes two big moving ranges, one going out and one coming back. Read the I chart to see which reading is the odd one.

Why not the overall standard deviation?

Now a trap that catches a lot of people. Why not just take the standard deviation of all the readings, and put the limits at three of those from the center? Because the overall standard deviation includes every shift, drift and jump in the data. If the process moved, the overall standard deviation grows, the limits widen, and the very change you're looking for hides inside them. The moving range only looks at neighbors, so it measures short-term variation, even when the process wanders.

Worked example 2: gloss by powder lot

Worked example two shows it. Every new powder lot, Priya sprays a test panel and reads its gloss. The target is eighty five gloss units, with a spec of eighty to ninety. Twenty four lots, about two a week. The average is eighty five point three. The twenty three moving ranges add up to twenty point seven, so M R bar is point nine. Ellen built her own limits with STDEV dot S on all twenty four lots: an overall standard deviation of one point four two. Three of those put her limits at eighty one point oh four and eighty nine point five six. Every lot is inside. Nothing to see?

Now Marcus does it the right way. Sigma hat is point nine divided by one point one two eight: about point eight. Nearly half of Ellen's number! The I chart limits are eighty five point three, plus or minus two point six six times point nine. That's eighty two point nine one to eighty seven point six nine. Lot twenty two, at eighty seven point nine, is above the limit. And look at the pattern: the first twelve lots all sit below the center line, and the last twelve all sit above it. The process shifted at lot thirteen!

Ellen calls the powder supplier. At lot thirteen, they switched to a new resin, without the notice every Brindlewood purchase order asks for. The new powder is glossier, about eighty six and a half instead of eighty four, and it's still inside the spec, so no lot is rejected. Ellen gets the notice rule back on track with the supplier. And since the change is now known and accepted, Marcus starts new limits from lots thirteen on: about eighty four point three to eighty eight point eight. They're temporary until twenty lots are in, then he recomputes.

Assumptions and cautions

Now the cautions. This chart has no averages, so the central limit theorem can't help it. If the data are strongly skewed, the limits are in the wrong place, and you'll get false alarms on the long side. So look at a histogram or a normal probability plot first, and if the data are skewed, use a transformation or limits from the right distribution. The capability for non-normal data video shows how. Next, the readings should be independent. Readings taken minutes apart, like oven temperature every minute, tend to follow each other. Then the moving ranges come out too small, the limits too tight, and the chart cries wolf.

How to read the result and decide

So how do you read the result and decide? In phase one, use twenty to twenty five readings or more, check the moving range chart, then the I chart. Remove a point only when you've found its cause, then recompute. In phase two, the limits stay fixed. A point outside, or a long run on one side of the center line, means look for a cause now. The run rules video covers the patterns. On the moving range chart, react only to points above the limit, because neighboring moving ranges share a reading. And remember, the I chart is slow to catch a small shift. Run rules help, or a special chart built for small shifts.

One more thing. Because an I chart plots single readings, in the same units as the spec, it's tempting to draw the spec limits on it. If you do, make them look completely different, and never use them in place of control limits. Control limits come from the process. Spec limits come from the customer. Our weld chart proved it: a reading inside the spec, but outside the control limit, found a problem before a chair ever failed!

Common mistakes

Now the common mistakes. One: computing limits with the overall standard deviation. Two: forgetting the moving ranges must stay in time order. Sort the data, and the moving ranges mean nothing. Three: dividing the sum of the moving ranges by the number of readings, instead of one fewer. Four: using an I chart when you could easily take subgroups, and throwing away information. Five: skipping the histogram, on skewed data. Six: calling two moving range spikes two problems, when it's one odd reading.

Recap

Let's recap. Use an I M R chart when you get one reading at a time. Moving range: the difference between neighbors. I chart: X bar, plus or minus two point six six M R bar. Moving range chart: upper limit three point two six seven M R bar. Sigma hat is M R bar over one point one two eight, never the overall standard deviation. Check for skew and for readings that follow each other. And a point outside the control limits is a signal, even when it's in spec!

Check yourself

Now, check yourself. Ellen charts moisture in the slat supplier's lumber, one reading per lot. The average is nine point oh percent, and M R bar is point six. What is the upper control limit on the I chart? A, ten point eight. B, ten point six. C, eleven point oh. Or D, nine point six. Pause the video if you want to think about it.

The answer is B, ten point six. Two point six six times point six is about one point six. Add it to nine point oh, and you get about ten point six percent. A used three times M R bar, and skipped dividing by d two. C used three point two six seven, which belongs on the moving range chart. And D just added M R bar.