Academy › Topic library › Flow, Pull and Cycle Time
Q-BOT ACADEMY · FREE VIDEO LESSON · 9 MIN
Flow, Pull and Cycle Time
Flow means work moves from step to step smoothly, without stopping and piling up in between. Pull means each step makes only what the next step has used, so the customer's pace sets the pace for everyone. And cycle time reduction means shrinking the time it takes work to get through the process. Lean puts all three together: what's needed, when it's needed, no piles.
In short
Takt time is the pace of demand, cycle time is how often a step finishes a unit, and lead time is the whole trip. Little's Law: lead time equals work in process divided by throughput. Flow moves work in small batches, and pull makes only what was used, with kanban signals that cap the pile. The bottleneck sets the pace. And quick changeovers, with S M E D, make small batches possible.
Check yourself
The coating area has seven hundred twenty frames waiting, and coating finishes three hundred sixty frames a day. Using Little's Law, about how long does a frame wait? A, half a day. B, two days. C, three hundred sixty days. Or D, one thousand eighty days.
Show the answer
The answer is B, two days. Lead time equals work in process divided by throughput. Seven hundred twenty divided by three hundred sixty is two. A flips the formula. C and D just subtract or add the numbers. That's flow, pull and cycle time. Questions? Ask Q-Bot right here in the Academy. And here's one for the road: Q-Bot tried to tell a joke in one big batch. By the punch line, everyone had already left. Now he tells them one piece at a time!
Where this topic is taught
This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.
Full lesson transcript
The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.
Intro
It's Thursday afternoon at Brindlewood Outdoor Furniture, and Gloria's Ridge bench station has run out of slats. Over at the slat mill, racks of Harbor chair slats are stacked to the ceiling, five days deep. But Ridge bench slats won't be milled until Friday. Dwayne throws up his hands. We've got slats everywhere! Just not the ones I need. Marcus nods. Then the problem isn't how many slats we make. It's how they flow.
Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: flow, pull and cycle time. We'll sort out three different times, then cover continuous flow, push versus pull, kanban, just in time, bottlenecks, and quick changeovers. Then we'll follow Brindlewood's slat mill, with real numbers.
What it is
So, what is it? Flow means work moves from step to step smoothly, without stopping and piling up in between. Pull means each step makes only what the next step has used, so the customer's pace sets the pace for everyone. And cycle time reduction means shrinking the time it takes work to get through the process. Lean puts all three together: what's needed, when it's needed, no piles.
First, three times that people mix up. Takt time is the pace of customer demand: available time divided by demand. Cycle time is how often a step actually finishes one unit. And lead time is how long one unit spends in the whole process, from start to finish, including all the waiting. A simple rule ties them together, Little's Law: lead time equals work in process divided by throughput. More stuff waiting means longer lead time!
Why it matters
Why does it matter? Because piles cost money. Every part on a rack is cash on the floor, taking up space and getting scratched. Piles hide problems: if a setting is wrong, you might make a whole week of bad parts before anyone uses one. And a long lead time means you can't react. Shorter lead time means faster answers for customers!
How it works
Let's go through the tools one at a time. First, continuous flow. Instead of moving a big batch all at once, you move one piece, or a small batch, to the next step as soon as it's done. Bad: weld a whole day of frames, then roll them all to coating, where they wait. Good: frames go to coating a few at a time, at the pace coating uses them. Less waiting, and a problem shows up on the next frame, not the next day.
Next, push versus pull. In a push system, each step makes parts to a schedule or a forecast, and pushes them downstream whether anyone needs them or not. In a pull system, nothing is made until the next step uses something. Bad: the mill runs whatever the weekly schedule says, and the racks fill up. Good: the mill replaces exactly what assembly just took. Pull means making the right thing!
Pull needs a signal, and the most common one is a kanban. Kanban is a Japanese word for a sign or a card. It can be a card, an empty cart, a marked floor space, or a second bin. When assembly empties a cart, the empty cart goes back, and that's the order to make one more cart. Two simple rules: no signal, no work. And the number of cards sets a hard limit on how much can pile up. Bad: carts with no limit. Good: four carts, and that's all!
Just in time puts pull to work across the whole chain: the right part, in the right amount, at the right time. But it needs stable processes and reliable suppliers. Bad: cut stock to zero overnight, when a machine breaks down every week. Good: shrink the buffers step by step, and fix each problem the smaller pile uncovers. Lower the water, and the rocks show up!
Every process has a bottleneck, the step with the least capacity. That step sets the pace for the whole line. Running other steps faster just builds piles in front of it. Brindlewood learned this when welding sped up, and six hundred frames piled up at the coating oven. Bad: reward every step for making more. Good: keep the bottleneck fed and running, and let everyone else work to its pace.
Now, quick changeovers. Small batches mean more changeovers, so changeovers have to be fast. The method is called S M E D, single minute exchange of die: get setups under ten minutes. Step one: separate internal work, which needs the machine stopped, from external work, which can be done while it's running. Step two: move as much as you can to external. Step three: streamline what's left. Bad: stop the machine, then go find the tools. Good: everything's ready on a cart before the machine stops!
Worked example: the slat mill
Now, the Brindlewood slat mill. Both shifts give the mill four thousand five hundred minutes a week. It makes eighteen hundred Harbor chair slat sets a week, two minutes each, and one hundred twenty Ridge bench slat sets, five minutes each. A changeover between them took sixty minutes, so the mill ran big batches: chair slats Monday through Thursday, bench slats on Friday. Marcus counted the racks each morning for a week: about eighteen hundred chair slat sets waiting, on average.
Little's Law gives the lead time. Assembly uses three hundred sixty chair slat sets a day. Eighteen hundred divided by three hundred sixty is five. So a slat waited about five days! Why not just switch every day? Count the minutes. Chair slats take thirty six hundred minutes, and bench slats six hundred. Ten changeovers a week, at sixty minutes each, adds six hundred more. That's forty eight hundred minutes, but the mill only has forty five hundred. Small batches won't fit, until the changeover gets faster.
So Lou and Marcus filmed a changeover. Of the sixty minutes, twenty five were external work done with the mill stopped: fetching knives from the tool crib and hunting for the wrench and the setup gauge. They moved all of it before the stop, onto a changeover cart. Then they streamlined the internal thirty five minutes. Lou pre-sets the knives on a spare cutter head, quick clamps replace four bolts, and a setup block replaces trial cuts. The changeover dropped from sixty minutes to fifteen!
Now the mill makes chair slats and bench slats every day, with ten fifteen minute changeovers a week. That's one hundred fifty minutes. Thirty six hundred plus six hundred plus one hundred fifty is forty three hundred fifty minutes, under forty five hundred! Then the pull: four kanban carts of ninety chair slat sets each, so never more than three hundred sixty waiting. Three hundred sixty divided by three hundred sixty a day is one day at most. Lead time went from five days to one, and Gloria has bench slats every day!
Common mistakes
Common mistakes. One: mixing up takt time, cycle time and lead time. Two: cutting inventory before the process is stable. Three: making a kanban with no limit, which is just push with cards. Four: speeding up a step that isn't the bottleneck. And five: shrinking batch sizes without shrinking changeover times first.
Recap
Let's recap. Takt time is the pace of demand, cycle time is how often a step finishes a unit, and lead time is the whole trip. Little's Law: lead time equals work in process divided by throughput. Flow moves work in small batches, and pull makes only what was used, with kanban signals that cap the pile. The bottleneck sets the pace. And quick changeovers, with S M E D, make small batches possible.
Check yourself
Now, check yourself. The coating area has seven hundred twenty frames waiting, and coating finishes three hundred sixty frames a day. Using Little's Law, about how long does a frame wait? A, half a day. B, two days. C, three hundred sixty days. Or D, one thousand eighty days. Pause the video if you want to think about it.
The answer is B, two days. Lead time equals work in process divided by throughput. Seven hundred twenty divided by three hundred sixty is two. A flips the formula. C and D just subtract or add the numbers.
That's flow, pull and cycle time. Questions? Ask Q-Bot right here in the Academy. And here's one for the road: Q-Bot tried to tell a joke in one big batch. By the punch line, everyone had already left. Now he tells them one piece at a time!