Academy › Topic library › Failure Mode and Effects Analysis (FMEA)
Q-BOT ACADEMY · FREE VIDEO LESSON · 9 MIN
Failure Mode and Effects Analysis (FMEA)
An F M E A is a step by step way to ask, before trouble starts: how could this go wrong, what would happen if it did, and what are we doing about it? A small team lists every way a step could fail, rates each one, and acts on the worst. There are two main kinds. A design F M E A asks how the product's design could fail. A process F M E A asks how the way we make it could fail.
In short
An F M E A finds how a design or process could fail, before it does. Each row has a failure mode, an effect, a cause and the current controls. Rate severity, occurrence and detection, one to ten. The R P N multiplies them, but always look at severity first. Then act, assign an owner, and score it again!
Check yourself
Failure mode X has severity three, occurrence eight, detection seven: an R P N of one hundred sixty eight. Failure mode Y has severity ten, occurrence two, detection five: an R P N of one hundred. Which should the team look at first? A, X, because its R P N is higher. B, Y, because a severity of ten comes first. C, neither, because both are under two hundred. Or D, whichever is cheaper to fix.
Show the answer
The answer is B. A severity of nine or ten means someone could get hurt, so it gets attention first, whatever the R P N says. A trusts the number alone. C invents a cut off that hides real risk. And D lets cost decide before safety. Fix Y first, then work on X!
Where this topic is taught
This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.
Full lesson transcript
The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.
Intro
Brindlewood, Monday morning. Rosa looks at her whiteboard. Two welding surprises this year. A worn contact tip that weakened a whole lot of frames. And a draft from the roll-up door that filled welds with tiny holes. Both were found after they cost money. Rosa asks Marcus a simple question: what's the next one? Can we find it before it happens?
Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: failure mode and effects analysis, or F M E A. We'll learn what it is, the parts of the worksheet, and how to score and rank the risks. Then we'll run one on Brindlewood's welding step, and find the next surprise before it finds us!
What it is
So, what is it? An F M E A is a step by step way to ask, before trouble starts: how could this go wrong, what would happen if it did, and what are we doing about it? A small team lists every way a step could fail, rates each one, and acts on the worst. There are two main kinds. A design F M E A asks how the product's design could fail. A process F M E A asks how the way we make it could fail.
Why it matters
Why does it matter? Most problem solving starts after a customer gets hurt or angry. An F M E A works before that. At Brindlewood, the weak welds cost a held lot and twenty two and a half hours of re-welding. A failure you prevent costs you a meeting. A failure your customer finds can cost you the customer!
How it works: the worksheet
Now, how it works. An F M E A lives on one worksheet, one row per failure mode. Across the top: the process step, the failure mode, the effect, severity, the cause, occurrence, the current controls, detection, and the risk score. Then actions, an owner, a date, and new scores. And it's built by a team: the people who do the work, plus quality, maintenance and engineering. Bad: one engineer filling it in at a desk. Good: the people who know the step, together!
First, the failure mode: the way the step could fail to do its job. Write it as a specific thing you could see or measure. Bad: weld problem. Good: weld has too little strength, below twelve hundred pounds of force on the pull test!
Second, the effect: what happens if the failure reaches the next step, or the customer. Then severity: how bad that effect is, on a scale of one to ten. One means nobody would notice. Ten means someone could get hurt, or a law is broken. Bad: rating severity by how often it happens. Good: rate only how bad the effect is. Severity is about the worst realistic outcome!
Third, the cause: why the failure would happen. Then occurrence: how likely that cause is, from one, almost never, to ten, almost every time. Use real data when you have it, like check sheets and scrap logs. Bad: the cause is operator error. Good: a specific cause you can act on, like a worn contact tip!
Fourth, the current controls: what we already do to prevent the cause, or to catch the failure. Then detection. And watch out, this scale runs backwards! One means we're almost certain to catch it before it leaves. Ten means we have no way to catch it at all. Bad: we inspect, so detection is a one. Good: ask honestly, would that check really catch this failure, every time?
Fifth, the risk score. The classic one is the risk priority number, or R P N: severity times occurrence times detection. With three one to ten scales, it runs from one to one thousand. But don't just sort by R P N! A failure that could hurt someone always deserves a look first, whatever its number. Newer F M E A guides use action priority instead: a table that looks at severity first, then occurrence, then detection, and calls each row high, medium or low.
Sixth, actions. For the top risks, decide what to change, who owns it, and by when. The best actions remove the cause, or make the mistake impossible. Next best, catch it sooner. Then, after the change, score the row again. Severity usually stays the same, because the effect would be just as bad. It's occurrence and detection that come down. Bad: action, be more careful. Good: a named change, an owner and a date!
Worked example: welding the frame
Now, the worked example. Marcus pulls together a team: two welders, Lou from maintenance, Priya from the lab, and Dwayne from assembly, who gets the frames next. The scope: one process step, welding the Harbor chair frame. That's eight welds per frame. They list five failure modes, and score each one, using the check sheets and pull test records.
Here are the scores. Weak weld from a worn contact tip: severity nine, occurrence three, detection five, an R P N of one hundred thirty five. A lumpy weld bead, from uneven travel speed: two, seven and nine, one hundred twenty six. A missed weld, when a welder is interrupted mid frame: ten, two and six, one hundred twenty. A frame out of square from a worn fixture clamp: six, four and three, seventy two. And porosity: seven, two and three, forty two.
Now look closely. By R P N alone, the lumpy bead ranks second. But it's a severity two: a cosmetic bump the coating mostly hides. The missed weld ranks third. Yet it's a severity ten: a leg could come loose under someone sitting in the chair! Severity first. So the team puts the missed weld at the top of the list, then the weak weld. The lumpy bead stays on the list, and they keep watching it.
The actions. For the missed weld, Lou adds a weld counter to each fixture: the clamps won't open until the gun has made all eight welds. That's mistake proofing! Occurrence drops to one, and detection to two. Ten times one times two: an R P N of twenty. For the weak weld, Lou now changes contact tips on a schedule, before they wear, and Priya pull tests one frame per station every shift. Nine times two times four: seventy two. Severity didn't change. The risk did!
Common mistakes
Common mistakes. One: doing it alone, at a desk. Two: vague failure modes and causes, like operator error. Three: sorting only by R P N, and missing a severity ten. Four: rating detection too kindly. Five: actions with no owner or date. And six: filling it in once, then filing it away. An F M E A is a living document. Update it whenever the process changes, or a new failure shows up!
Recap
Let's recap. An F M E A finds how a design or process could fail, before it does. Each row has a failure mode, an effect, a cause and the current controls. Rate severity, occurrence and detection, one to ten. The R P N multiplies them, but always look at severity first. Then act, assign an owner, and score it again!
Check yourself
Now, check yourself. Failure mode X has severity three, occurrence eight, detection seven: an R P N of one hundred sixty eight. Failure mode Y has severity ten, occurrence two, detection five: an R P N of one hundred. Which should the team look at first? A, X, because its R P N is higher. B, Y, because a severity of ten comes first. C, neither, because both are under two hundred. Or D, whichever is cheaper to fix. Pause the video if you want to think about it.
The answer is B. A severity of nine or ten means someone could get hurt, so it gets attention first, whatever the R P N says. A trusts the number alone. C invents a cut off that hides real risk. And D lets cost decide before safety. Fix Y first, then work on X!
Wrap-up
That's failure mode and effects analysis. Questions? Ask Q-Bot right here in the Academy. And one for the road: why did Q-Bot rate his own jokes a severity one? Because nobody ever noticed them!
Independent study material; not affiliated with or endorsed by ASQ. Body of Knowledge codes identify where the topic appears in each certification's published outline.