Control Plans

A control plan is one document that says how a process is kept on target, every shift, by anyone. For each important step it lists what to control, the specification, how to measure it, how many and how often, how it's controlled, what to do when something goes wrong, and who does it. It's the end of an improvement project, and the start of everyday life for the process.

8:19 · Q-Bot · narrated, with worked example and a check-yourself question

In short

A control plan keeps a process on target, every shift, by anyone. Each row names the characteristic, the specification and measurement method, the sample size and frequency, and the control method. The reaction plan says exactly what to do when a check fails, and who does it. And it's a living document, signed and owned by the process owner.

Check yourself

A frame reads below the minimum thickness. Which part of the control plan tells the operator what to do next? A: the specification. B: the sample size and frequency. C: the reaction plan. Or D: the process F M E A.

Show the answer

The answer is C, the reaction plan. The specification tells you the reading is bad, the frequency tells you when to check, and the F M E A helped decide what goes in the plan. But only the reaction plan says: stop, hold, measure, fix and record!

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Brindlewood, the week Lou went on vacation. By Thursday, thin spots were back on the Harbor chairs. Fifty two chairs went back for a second coat that week. Normal since the coating project? About fifteen. Rosa holds up the rework sheet. We fixed this! Why is it back? Marcus sighs. Because part of the fix lived in Lou's head. Stripping the hooks every two days was on his list, in his office, and nobody else knew!

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: control plans. We'll see what a control plan is, the five things every row needs, and we'll build a real one for the Brindlewood coating line, with numbers!

What it is

So, what is it? A control plan is one document that says how a process is kept on target, every shift, by anyone. For each important step it lists what to control, the specification, how to measure it, how many and how often, how it's controlled, what to do when something goes wrong, and who does it. It's the end of an improvement project, and the start of everyday life for the process.

Why it matters

Why does it matter? Because gains fade! People change jobs, go on vacation, or forget. A fix that lives in someone's head, or on a sticky note, slowly slips away. Lou's one week off cost about thirty seven extra reworks, at eighteen dollars each. That's six hundred sixty six dollars, from one missing line on a list. A control plan holds the gains, and it hands the process cleanly back to its owner.

How it works: five parts

Now, how it works, one part at a time. First: what to control. There are two kinds of characteristics. A product characteristic is something about the thing you make, like coating thickness on the chair. A process characteristic is a knob that makes it, like gun voltage or oven temperature. Bad: only checking the chair at the very end. Good: control the knobs that make the result, and check the result too!

Second: the specification and the measurement method. Bad: a row that just says, check the coating. Check it how? Against what? Good: coating thickness, two and a half to four mils, target three, measured with the coating thickness gauge on the flat face and the inside corner. And the gauge has passed a gauge study, so the numbers can be trusted.

Third: sample size and frequency. How many, and how often? Bad: check regularly. Good: ten frames a shift, spread out through the shift. Here's the trick. The more often you check, the fewer parts are in doubt when something goes wrong. So pick a frequency you can afford, that still catches problems while they're small!

Fourth: the control method. That's how the step is watched. It could be a control chart, a signed start-up checklist, or mistake-proofing, like the weld counter that won't open the clamps until all eight welds are made. Bad: a method that says, be careful. Good: a method that works even on a bad day, or a new person's first day.

Fifth, and most important: the reaction plan, and who owns it. The reaction plan says exactly what to do when a check fails. Bad: notify supervisor. Then what? Good: stop the line, put a red hold tag on everything since the last good check, measure it, fix the cause, and write it down. And every row gets a named role, with a backup. Not everyone, and not quality. A real person's job!

Where do the rows come from? From the process F M E A, the failure modes with the highest risk, and from everything the improvement project learned. A control plan can be written for a prototype, for a pre-launch trial, or for full production. And it's a living document. When the process changes, the control plan changes too, through change control. The process owner signs it, and from then on, it's theirs.

Worked example: the coating line

Now, the worked example. Marcus and the coating supervisor sit down with Lou, Priya and two coating operators. They gather every fix from the last few projects into one control plan for the coating line. Hooks: stripped every two days, with the coating lead as Lou's backup. Gun set-up: sixty kilovolts, twenty five P S I of air, the powder flow setting, a clean nozzle and a ground check, all on the signed start-up checklist, before the first frame is hung.

Next rows. The spacing bar notch matches the product, checked at every changeover. The oven runs at three hundred sixty degrees, recipe revision D, read every morning on Lou's chart. And coating thickness, two and a half to four mils, ten frames a shift, on the X bar and S chart. Six rows in all. One page, on a clipboard, right at the line. The coating supervisor signs it as the process owner.

Now the numbers behind the frequency. The line coats about eighteen hundred frames a week, over ten shifts. That's one hundred eighty frames a shift. Ten checks a shift means one check about every eighteen frames. So if a check fails, only about eighteen frames are in doubt. If Priya measured all ten at the end of the shift, the whole one hundred eighty would be in doubt. That's ten times more to sort!

Week four. Second shift, eight o'clock. A frame reads two point four mils, below the two and a half minimum. This time, nobody guesses. The operator stops hanging frames, puts a red hold tag on the eighteen frames since the last good check, and calls the shift lead. They measure all eighteen. Seven are thin. Seven recoats at eighteen dollars each: one hundred twenty six dollars. And the cause? A kinked powder hose behind the booth. Fixed in ten minutes, and written down.

Compare that with Lou's vacation week: six hundred sixty six dollars of extra rework, and a mystery. This time: one hundred twenty six dollars, one cause, found the same night. Rosa reads the record the next morning. So the plan worked, and Lou was home asleep? Exactly. That's the point of a control plan. The process holds its gains, even when the expert isn't there!

Common mistakes

Common mistakes. One: writing the plan, then filing it in a drawer. Two: reaction plans that just say, notify supervisor. Three: controlling only the final product, and none of the knobs. Four: no named owner, or no backup. Five: measuring with a gauge nobody has checked. And six: never updating the plan when the process changes!

Recap

Let's recap. A control plan keeps a process on target, every shift, by anyone. Each row names the characteristic, the specification and measurement method, the sample size and frequency, and the control method. The reaction plan says exactly what to do when a check fails, and who does it. And it's a living document, signed and owned by the process owner.

Check yourself

Now, check yourself. A frame reads below the minimum thickness. Which part of the control plan tells the operator what to do next? A: the specification. B: the sample size and frequency. C: the reaction plan. Or D: the process F M E A. Pause the video if you want to think about it.

The answer is C, the reaction plan. The specification tells you the reading is bad, the frequency tells you when to check, and the F M E A helped decide what goes in the plan. But only the reaction plan says: stop, hold, measure, fix and record!

Wrap-up

That's control plans. Questions? Ask Q-Bot right here in the Academy. And one for the road: I wrote a control plan for my jokes. Reaction plan: if nobody laughs, stop, hold the next joke, and find the root cause. It's usually me!