Choosing Projects and the Project Charter

A project is temporary work with a start, an end, and a goal. Every project has a life cycle: start it, plan it, do the work while you watch the progress, then close it. Project selection is how you decide which problems deserve a team's time. The project charter is the first document of the start. It's a one page agreement between the sponsor and the team: why, what problem, what goal, what's in and out, who, and by when.

9:14 · Q-Bot · narrated, with worked example and a check-yourself question

In short

Choose projects from data: a measured gap, tied to a goal, an unknown cause, a sponsor, and a size you can finish. Rank the finalists with a weighted selection matrix. Then write the charter: business case, problem statement, smart goal, scope in and out, team and roles, and milestones with sign off. One page, agreed and signed, before the work starts.

Check yourself

Which one is the best problem statement? A: shipping is slow because the packers rush. B: we need a new conveyor in packing. C: over eight weeks, three percent of Harbor chairs shipped late, against a target of half a percent, costing about sixty-seven thousand five hundred dollars a year. Or D: make our customers happier.

Show the answer

The answer is C. It says what, where, when and how big, with the target and the cost, and it doesn't guess the cause. A names a cause and blames people. B is a solution. And D is a wish, with no number to measure.

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Brindlewood, Monday morning. Rosa's whiteboard holds eleven project ideas, and everyone has a favorite. Lou wants a robot spray booth. Hannah wants late shipments fixed. Someone wants a new break room microwave. And everyone remembers last spring's project, called fix shipping. It grew to cover labels, forklifts and dock doors, ran five months, and quietly faded away. Nobody could say what it was supposed to fix!

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: choosing projects and the project charter. We'll learn how to pick the right problem, and how to write the one page agreement that keeps a project on track. Then we'll pick Brindlewood's next project, and write its charter!

What it is

So, what is it? A project is temporary work with a start, an end, and a goal. Every project has a life cycle: start it, plan it, do the work while you watch the progress, then close it. Project selection is how you decide which problems deserve a team's time. The project charter is the first document of the start. It's a one page agreement between the sponsor and the team: why, what problem, what goal, what's in and out, who, and by when.

Why it matters

Why does it matter? Because a team's time is expensive. Pick the wrong problem, and good people work hard on something that doesn't matter. Skip the charter, and you get fix shipping: no clear problem, no goal, no boundaries, five months of meetings, and nothing to show for it. A good charter takes about an hour to write. It can save months!

How it works: choosing the project

Now, how it works, starting with choosing the project. Good ideas come from data, not from the loudest voice. Look at complaints and surveys, the cost of quality, audit findings, scrap and rework, delivery measures, and the plant's goals. Bad: the project is whatever the boss thought of in the shower. Good: the project starts from a number that's hurting a customer or the business!

Next, screen each idea with a few questions. Is there a real gap, measured with data? Is it tied to a plant goal? Is the cause still unknown? If you already know the fix, just do it. Can a team finish it in about three to six months? And is there a sponsor who owns the problem? Bad: a robot spray booth. That's a solution looking for a problem. Good: late shipments, a measured gap with an unknown cause. And the microwave? Just buy it!

Then rank what's left with a selection matrix. Pick a few criteria, give each a weight, and score every idea from one to nine. Multiply each score by its weight, and add them up. Bad: we pick the idea with the most passionate supporter. Good: weighted scores on the wall, so everyone sees why one idea wins!

How it works: the charter, part by part

Now the charter, one part at a time. Part one: the business case. Why this project, why now? Tie it to money, customers, or a plant goal. Bad: it would be nice to improve shipping. Good: late shipments cost about sixty-seven thousand five hundred dollars a year, and our biggest garden center account is watching.

Part two: the problem statement. It says what's wrong, where, since when, and how big, with numbers. It never names a cause, a solution, or a person to blame. Bad: shipping is slow because the packers rush, so we need a new conveyor. That's a cause, a solution and blame, all in one sentence! Good: over the last eight weeks, an average of fifty four of eighteen hundred Harbor chairs a week shipped after the promised date.

Part three: the goal statement. Make it smart: specific, measurable, achievable, relevant, and time bound. Bad: reduce late shipments. By how much? By when? Good: cut late Harbor chair shipments from three percent to half a percent or less, within sixteen weeks!

Part four: the scope. Write down what's in, and just as important, what's out. A S I P O C or a Pareto chart helps you draw that line. Bad: everything to do with shipping. That's how last spring's project swallowed forklifts and dock doors. Good: in scope, Harbor chairs, from the order coming in to the truck leaving the dock, both shifts. Out of scope, for now: tables, benches, and the trucking company's drive time.

Part five: the team and roles. The sponsor owns the problem, removes roadblocks, and signs. The leader runs the project. The process owner lives with the result. Members come from the areas the problem touches. Bad: whoever was free on Tuesday. Good: the right people, with their time agreed by their bosses.

Part six: milestones and sign off. Put dates on the big steps, and plan a review with the sponsor at the end of each one. Those reviews are often called tollgates. Then the sponsor and the leader sign. Bad: we'll be done when we're done. Good: five dated phases, five reviews, two signatures. If the scope changes later, the charter is revised and signed again!

Worked example: Brindlewood's next project

Now, the worked example. Rosa's team screens the eleven ideas down to three. The weights: customer impact point four, savings point three, chance of success point three. Late shipments score nine, seven and eight. That's three point six, plus two point one, plus two point four, for a total of eight point one. Powder overspray scores two, eight and six, for a total of five point oh. And the Ridge bench slat color match scores six, four and five, for five point one. Late shipments win, clearly!

Marcus drafts the charter with Rosa. The problem: over the last eight weeks, an average of fifty four of eighteen hundred Harbor chairs a week shipped late. That's three percent, against a target of half a percent or less. The business case: each late chair costs about twenty five dollars in rush freight and credits. Fifty four times twenty five is thirteen hundred fifty dollars a week. Times fifty working weeks, that's sixty-seven thousand five hundred dollars a year!

The goal: half a percent is nine chairs a week. Fifty four down to nine is forty five fewer late chairs a week, worth about fifty six thousand two hundred fifty dollars a year. The scope: Harbor chairs, order to dock, both shifts. The team: Rosa sponsor, Marcus leader, Dwayne process owner, plus Hannah, Ellen, and a shipping clerk from each shift. The schedule: define two weeks, measure three, analyze three, improve five, control three. Sixteen weeks! Rosa and Marcus sign. In week three, someone asks to add the Ridge bench. Marcus puts it in the parking lot, and Rosa says it waits for the next project.

Common mistakes

Common mistakes. One: picking projects by opinion instead of data. Two: a solution disguised as a project, like the robot booth. Three: a problem statement that blames someone or names the cause. Four: a goal with no number or no date. Five: a scope so big it can't be finished. And six: a charter that's filed and never read again!

Recap

Let's recap. Choose projects from data: a measured gap, tied to a goal, an unknown cause, a sponsor, and a size you can finish. Rank the finalists with a weighted selection matrix. Then write the charter: business case, problem statement, smart goal, scope in and out, team and roles, and milestones with sign off. One page, agreed and signed, before the work starts.

Check yourself

Now, check yourself. Which one is the best problem statement? A: shipping is slow because the packers rush. B: we need a new conveyor in packing. C: over eight weeks, three percent of Harbor chairs shipped late, against a target of half a percent, costing about sixty-seven thousand five hundred dollars a year. Or D: make our customers happier. Pause the video if you want to think about it.

The answer is C. It says what, where, when and how big, with the target and the cost, and it doesn't guess the cause. A names a cause and blames people. B is a solution. And D is a wish, with no number to measure.

Wrap-up

That's choosing projects and the project charter. Questions? Ask Q-Bot right here in the Academy. And one for the road: why did the project charter bring a fence to the meeting? To keep its scope from wandering off!