Academy › Topic library › Building and Managing the Project Pipeline

Q-BOT ACADEMY · FREE VIDEO LESSON · 10 MIN

Building and Managing the Project Pipeline

Building and Managing the Project Pipeline is the flow of improvement work, from idea to result. Ideas come in. They get qualified, ranked and chartered. The active projects run, they close, and the gains get handed to a process owner. Think of it as a production line where the product is improvement. It needs the right amount of work in it, at the right time.

9:31 · Q-Bot · narrated, with worked example and a check-yourself question

In short

Find ideas everywhere, and qualify them: a just-do-it, a real project, or not now. Engage everyone the project touches, especially the managers who control the time. Rank with a weighted matrix, and manage the risk of each project and of the mix. Start only what belt hours can carry, and keep a ready queue. Give every project a budget, a forecast and a cash flow, and track it in red, amber and green.

Check yourself

Brindlewood's twelve qualified projects need nineteen hundred twenty belt hours, but the belts have fourteen hundred fifty six. What should the steering team do? A, start all twelve, and ask the belts to work harder. B, start the top nine by score, and keep three in a ready queue. C, start the nine easiest projects, whatever their scores. D, wait until there's time for all twelve.

Show the answer

The answer is B! The top-ranked projects start first, the work fits the hours, and the next project is ready the moment one closes. Picked A? Overloading the belts is how fourteen projects turned into eight stalled ones. That's building and managing the project pipeline. Questions? Ask Q-Bot right here in the Academy. Why was the project pipeline so calm? It had learned to go with the flow!

Where this topic is taught

This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.

Full lesson transcript

The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.

Intro

Brindlewood, January. On the steering team's wall, Marcus has stuck up twenty three improvement ideas on sticky notes. Dwayne counts them and laughs. We can't do twenty three! Rosa nods. Then which nine? And if one of them starts going off the rails in March, how will we know before December?

Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: building and managing the project pipeline! We'll find and rank project ideas, fit them to belt hours, put money numbers on them, and keep them on track.

What it is

So, what is a project pipeline? It's the flow of improvement work, from idea to result. Ideas come in. They get qualified, ranked and chartered. The active projects run, they close, and the gains get handed to a process owner. Think of it as a production line where the product is improvement. It needs the right amount of work in it, at the right time.

Why it matters

Why does it matter? Starve the pipeline, and belts sit idle. Overload it, and every project crawls. Fill it with the wrong projects, and the savings never reach the scorecard. A good pipeline keeps the belts busy on the work that matters most!

How it works

Now, how it works. Step one: find the opportunities. Look where the pain already shows: complaints, the cost of quality report, scorecard gaps, audit findings, ideas from the floor. When the usual answers run dry, use creativity tools. Brainstorming. Brainwriting, where everyone writes ideas silently first. Scamper: what could you substitute, combine, adapt, or remove? Bad: waiting for someone to bring you a project. Good: every idea source gets checked, every month!

Step two: qualify each idea. Is it really a project? If the cause and the fix are already known, it's a just-do-it. Hand it to the area. A real project needs a problem with an unknown cause, a link to a strategic goal, a measure you can collect data on, a scope one team can handle in a few months, and a champion willing to sponsor it. Bad: a vague idea, like fix quality. Good: cut coating recoats from fifty a month to ten!

Step three: check who the project touches. Most projects cross departments. Ask who gains, who pays, and who has to change. Map the stakeholders by how much influence they have, and how much they support the project. Then engage the managers. Executives sponsor the project, but middle managers control people's time. Give them a seat at the tollgate reviews, and give them credit for the results!

Step four: rank the qualified projects. Use a weighted scoring matrix. Score each project from one to five on benefit, alignment to the strategy, ease, and risk, where five means low risk. Weight what matters most. At Brindlewood: benefit forty percent, alignment thirty, ease twenty, and risk ten. Multiply, add, and sort. Bad: the loudest manager goes first. Good: the scores go first, and the team can see why!

Step five: manage risk, for each project and for the whole pipeline. For each project, list what could go wrong, score how likely and how bad it is, and plan a response for the big ones. For the pipeline, look at the mix. All nine projects in welding? That area can't absorb that much change at once. Spread the risk, and mix quick wins with longer, bigger projects.

Step six: match demand to supply. Demand is the belt hours the projects need. Supply is the belt hours you really have. Never start more than supply can carry. Set a limit on how many projects each belt runs at once. The rest wait in a ready queue, already qualified and ranked. When a project closes, the next one in line starts. That's pipeline management: steady flow, not a traffic jam!

Step seven: the money. Every project gets a budget, and a month-by-month forecast of its savings. Know your costing terms. A one-time cost, like a new tool, is paid once. A variable cost, like powder, changes with every unit you make. Hard savings show up in the bank. Soft savings, like freed-up time, only count if you use that time. Then lay out the cash flow: when money goes out, and when it comes back. The month it all evens out is the payback point.

Step eight: oversight, once projects are running. The principles: a clear scope, a schedule, the right resources, and a quality result. Measure each project against its plan. Are the tollgates on time? Is the spending on budget? Are the savings on forecast? Show it on one tracker, in red, amber and green, and report status on one page, the same way every month, so leaders spot trouble in seconds!

Step nine: step in, and correct. When a project turns red, the master black belt intervenes, starting light. Ask questions. Coach the belt. Facilitate a stuck team. Escalate to the champion to clear a roadblock. Then pick a corrective action: re-plan, add help, shrink the scope, or stop the project. Stopping a project that can't win frees hours for one that can!

Worked example at Brindlewood

Let's work it at Brindlewood. Twenty three ideas. Six are just-do-its, with a known fix, so they go straight to the areas. Five are dropped: no link to a goal, or no way to measure them. That leaves twelve qualified projects. The team scores them. Coating recoats: four, five, four and four, for a weighted score of four point three. Clearer assembly instructions: three, four, five and five, that's three point nine. A new office report: two, one, three and four, just two point one.

Now supply and demand. Four belts, eight hours a week, forty eight weeks: fifteen hundred thirty six belt hours. One project carried over from last year still needs about eighty, which leaves fourteen hundred fifty six. Twelve projects at about a hundred sixty hours each would need nineteen hundred twenty. That's room for about nine point one projects. So the top nine go on this year's plan, no belt runs more than two at a time, and three wait in the ready queue!

Next, the cash flow for coating recoats. A booth airflow upgrade costs eighteen thousand dollars, paid in month one. Recoats should drop from fifty frames a month to ten, and each recoat costs about seventy five dollars in powder, gas and labor. That's forty times seventy five, or three thousand dollars a month in hard savings, starting in month three. Six months of savings cover the eighteen thousand, so payback comes at the end of month eight. And the first year nets twelve thousand dollars!

Then, in March, the tracker turns red. The coating project's Measure tollgate was planned for week six, and it's now week nine. Lou, the belt, keeps getting pulled onto oven breakdowns. Marcus asks questions, then goes to the champion, who protects Lou's eight hours a week. The team re-plans, and the savings now start in month four. Payback moves to month nine, and the first year nets nine thousand dollars. Caught in March, not December!

Common mistakes

Common mistakes. Starting every idea at once. Running just-do-its as full projects. Ranking by who shouts loudest. Counting soft savings as cash. Never updating the forecast. And letting a red project stay red for months.

Recap

Let's recap. Find ideas everywhere, and qualify them: a just-do-it, a real project, or not now. Engage everyone the project touches, especially the managers who control the time. Rank with a weighted matrix, and manage the risk of each project and of the mix. Start only what belt hours can carry, and keep a ready queue. Give every project a budget, a forecast and a cash flow, and track it in red, amber and green.

Check yourself

Check yourself. Brindlewood's twelve qualified projects need nineteen hundred twenty belt hours, but the belts have fourteen hundred fifty six. What should the steering team do? A, start all twelve, and ask the belts to work harder. B, start the top nine by score, and keep three in a ready queue. C, start the nine easiest projects, whatever their scores. D, wait until there's time for all twelve. Pause the video if you want to think about it.

The answer is B! The top-ranked projects start first, the work fits the hours, and the next project is ready the moment one closes. Picked A? Overloading the belts is how fourteen projects turned into eight stalled ones.

That's building and managing the project pipeline. Questions? Ask Q-Bot right here in the Academy. Why was the project pipeline so calm? It had learned to go with the flow!