Acceptance sampling means deciding about a whole lot from a sample. A sampling plan has three numbers: the sample size, n, the acceptance number, and the rejection number. Inspect n pieces. If the defectives found are at or below the acceptance number, accept the lot. At or above the rejection number, reject it. That's a single sampling plan. A double plan allows a second sample when the first is in between, and multiple and sequential plans keep going, one small sample at a time.
In short
A sampling plan is a sample size, an acceptance number and a rejection number. The O C curve shows the chance of accepting at every quality level. The A Q L and producer's risk protect the supplier; the L T P D and consumer's risk protect you. Z one point four counts, with code letters and switching rules. Z one point nine measures, with smaller samples and a normal shape. And the A O Q L is the worst average that gets through.
Check yourself
A plan says: sample eighty, accept on two, reject on three. Priya finds three defectives in the sample. What happens to the lot? A: accept it, three is close enough. B: reject it. C: take a second sample. D: switch to reduced inspection.
Show the answer
The answer is B, reject the lot! Three reaches the rejection number. C would only apply to a double sampling plan, and this one is single. A ignores the plan. And D goes the wrong way: a rejected lot never earns reduced inspection. That's acceptance sampling plans. Questions? Ask Q-Bot right here in the Academy. And one for the road: I tried acceptance sampling on my jokes. I told one hundred twenty five of them, and the audience rejected the lot!
Where this topic is taught
This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.
Full lesson transcript
The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.
Intro
Brindlewood, receiving dock, a Monday morning. A truck from the tube mill drops off nineteen hundred twenty aluminum tubes. The dock pulls five tubes off the top, sees no dents, and signs for the lot. By Wednesday, Dwayne's welders are setting dented tubes aside, about one in twenty! Ellen asks Priya how the lot passed. Priya sighs: five tubes from the top. A lot like that passes our check about three times out of four.
Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: acceptance sampling plans! What a plan is, the O C curve that shows how well it protects you, and the two standards most plants use: Z one point four for counts, and Z one point nine for measurements. If sampling itself is new to you, start with the sampling video.
What it is
So, what is it? Acceptance sampling means deciding about a whole lot from a sample. A sampling plan has three numbers: the sample size, n, the acceptance number, and the rejection number. Inspect n pieces. If the defectives found are at or below the acceptance number, accept the lot. At or above the rejection number, reject it. That's a single sampling plan. A double plan allows a second sample when the first is in between, and multiple and sequential plans keep going, one small sample at a time.
Why it matters
Why does it matter? Checking every tube costs time and money, and tired eyes still miss things. But a weak plan is worse: it looks like inspection while it waves bad lots through. That dented lot cost Dwayne's line a day of sorting. Sampling never proves a lot is good. It manages risk, and you should know exactly how much!
How it works
Now, how it works, one piece at a time. First: the words. The A Q L, the acceptable quality level, is the worst average quality you'd still call satisfactory, like one percent defective. The producer's risk, alpha, is the chance a good lot at the A Q L gets rejected. The L T P D, also called the R Q L, the rejectable quality level, is a quality so bad you want it rejected nearly every time. The consumer's risk, beta, is the chance a lot that bad gets accepted anyway. Bad: thinking an A Q L of one percent promises every lot is ninety nine percent good. Good: it's a target for the process average!
Second: the O C curve, the operating characteristic curve. Across the bottom, the lot's true percent defective. Up the side, the chance the plan accepts it. A perfect plan would be a cliff: accept every good lot, reject every bad one. Real plans slope, and a bigger sample makes the slope steeper. Bad: picking a plan without ever looking at its curve. Good: reading off the chance of accepting the quality you're worried about!
Third: the Z one point four standard, for attributes, counting defectives or defects. Step one: your lot size and inspection level, usually general level two, give a code letter. Step two: the code letter and your A Q L give the sample size, the acceptance number and the rejection number. Bad: making up a plan like, check five, accept on zero. Good: a plan from the standard, with a known O C curve behind it.
Fourth: switching rules, the part people skip. Start on normal inspection. If two of five lots in a row are rejected, switch to tightened, with stricter acceptance numbers. Five lots in a row accepted on tightened, go back to normal. A long, steady run of good lots, with the people in charge agreeing, can earn reduced inspection, with smaller samples. And if five lots are rejected while on tightened, stop accepting until the supplier fixes the process. Bad: using the tables and ignoring the switching rules. Good: the switching rules protect you when a supplier slips!
Fifth: A O Q, the average outgoing quality. Suppose rejected lots are sorted one hundred percent, and every defective is replaced. The A O Q is the average percent defective that gets through. It's low when incoming quality is good, and also low when it's terrible, because those lots get sorted. In between it peaks, and that peak is the A O Q L, the average outgoing quality limit: the worst long run average that gets through.
Sixth: the Z one point nine standard, for variables, when you measure. Take the sample's average and standard deviation, and see how many standard deviations the average sits from the spec limit. Compare that to a number from the table called k. Far enough away, accept. Too close, reject. Measurements carry more information, so the samples are smaller for the same protection. But it assumes a normal curve. Bad: using it on lumpy, two hump data. Good: checking the shape first!
Worked example: tube lots
Now the worked example at Brindlewood. Marcus and Priya set up a dent plan for tube lots. The lot is nineteen hundred twenty tubes, which falls in the range twelve hundred one to thirty two hundred. At general level two, that's code letter K. Ellen and the tube mill agree on an A Q L of one percent. Code K at one percent, on normal inspection: sample one hundred twenty five tubes, accept on three or fewer dented, reject on four or more. Priya pulls them at random from every bundle, not off the top!
Here's that plan's O C curve, checked with the binomial. A lot with one percent dented: accepted about ninety six percent of the time, so the producer's risk is about four percent. Two percent: about seventy six percent. Three percent: about forty eight. And a lot like that Monday lot, five percent dented: accepted only about twelve percent of the time. The old five tube check accepted it seventy seven percent of the time! The plan's ten percent point, its L T P D, is about five point three percent.
Now the A O Q. The tube mill agrees to sort every rejected lot. At one percent incoming, about point nine percent gets through on average. At five percent incoming, most lots get sorted, so only about point six percent gets through. The peak comes at about two and a third percent incoming: the A O Q L is about one point four five percent, about one tube in seventy at worst.
Two months later, two of five lots in a row are rejected. Priya switches to tightened: still one hundred twenty five tubes, but accept on two or fewer. A five percent lot now passes only about five percent of the time. Ellen sends a corrective action request, the mill fixes its strapping, five lots in a row pass, and Priya switches back to normal.
Priya also tries a variables plan for slat thickness, spec eighteen point five to nineteen point five millimeters. Say the table gives k of one point eight, just for illustration. Her sample averages nineteen point oh two, with a standard deviation of point one five. Upper limit minus the average, divided by the standard deviation: three point two. The lower side: about three point four seven. Both above one point eight: accept! A later lot averages nineteen point two eight: only about one point four seven below the upper limit. Under one point eight, so reject, even if every slat she measured was in spec.
Common mistakes
Common mistakes. Taking the sample off the top of the pile. Treating the A Q L as a guarantee for every lot. Skipping the switching rules. Using a variables plan on data that isn't normal. Shipping the defectives you found in the sample. And forgetting that sampling never improves quality: it only finds out about it. The real fix is the supplier's process!
Recap
Let's recap. A sampling plan is a sample size, an acceptance number and a rejection number. The O C curve shows the chance of accepting at every quality level. The A Q L and producer's risk protect the supplier; the L T P D and consumer's risk protect you. Z one point four counts, with code letters and switching rules. Z one point nine measures, with smaller samples and a normal shape. And the A O Q L is the worst average that gets through.
Check yourself
Check yourself. A plan says: sample eighty, accept on two, reject on three. Priya finds three defectives in the sample. What happens to the lot? A: accept it, three is close enough. B: reject it. C: take a second sample. D: switch to reduced inspection. Pause the video if you want to think about it.
The answer is B, reject the lot! Three reaches the rejection number. C would only apply to a double sampling plan, and this one is single. A ignores the plan. And D goes the wrong way: a rejected lot never earns reduced inspection.