Q-BOT ACADEMY · FREE VIDEO LESSON · 10 MIN
5S, Visual Management and Standard Work
Three tools that work together. Five S is a way to organize a workplace, so there's a place for everything, and everything is in its place. Visual management makes the status of the work clear at a glance: what's normal, what's not, and what to do about it. And standard work is the current best way to do a job, written down: the steps, in order, with times, so everyone does it the same way. Five S is the foundation, and the other two are built on top of it!
In short
Five S: sort, set in order, shine, standardize and sustain. Sustain is the hardest, so make it a habit. Visual management shows normal versus not normal at a glance, and the best visuals trigger an action, like an andon light or a kanban. Standard work has three parts: takt time, the work sequence, and standard work in process. And standard work is the baseline for every improvement!
Check yourself
A packing cell has three thousand six hundred available minutes a week, and customers need twelve hundred units a week. What is the takt time? A, one third of a minute. B, three minutes. C, thirty minutes. Or D, four thousand eight hundred minutes.
Show the answer
The answer is B, three minutes. Takt time is available time divided by demand. Three thousand six hundred divided by twelve hundred is three. A flips the formula: demand divided by time gives units per minute, not minutes per unit. C and D don't follow the formula at all. So every station's work has to fit inside three minutes.
Where this topic is taught
This lesson is part of every free Academy course whose Body of Knowledge covers it. Each course puts it in context, with exercises and checks.
Full lesson transcript
The narration from the video, by chapter. Brindlewood Outdoor Furniture and its people are a fictional company used in every Q-Bot Academy lesson.
Intro
Brindlewood, Tuesday night, second shift, in the cutting and bending cell. Nate, the bender operator, needs the angle gauge to check a bend. It isn't on his bench. It isn't in the drawer. Twenty minutes later, Lou finds it under a pile of tube offcuts, next to three bending dies nobody has used in a year. Meanwhile, over in assembly, Dwayne's crew is standing around, waiting for chair legs.
Hey there, I'm Q-Bot. Welcome to the Q-Bot Academy. Today: five S, visual management and standard work. We'll walk through the five S steps, see how a workplace can talk to you at a glance, and learn the three parts of standard work. Then we'll fix that cell, with real numbers!
What it is
So, what are they? Three tools that work together. Five S is a way to organize a workplace, so there's a place for everything, and everything is in its place. Visual management makes the status of the work clear at a glance: what's normal, what's not, and what to do about it. And standard work is the current best way to do a job, written down: the steps, in order, with times, so everyone does it the same way. Five S is the foundation, and the other two are built on top of it!
Why it matters
Why does it matter? Priya timed the cutting and bending cell for one week, ten shifts. Searching for tools, dies and gauges took four hundred minutes. That's forty minutes, every shift, with a machine standing still. And on second shift, the bender took longer for each chair than the line could afford, so assembly ran short of legs almost every night. Rosa asked the big question: what is this costing us?
How it works: the five S steps
Now, how it works. First, the five S steps, one at a time. One, sort: keep what the job needs, and remove everything else. Anything you're not sure about gets a red tag and goes to a holding area for a couple of weeks. If nobody asks for it, it leaves. Two, set in order: a place for everything, with the things used most kept closest. Bad: tools piled in a shared drawer. Good: a shadow board, where every tool has its own outline, so a missing tool shows up as an empty shape!
Three, shine: clean the area, and inspect while you clean. Cleaning is how you spot a leak or a loose bolt early. Four, standardize: write down how the area should look, with a photo and a short checklist, so the first three steps become the normal way. And five, sustain: make it a habit, with a quick, regular five S audit and leaders who walk the floor. Bad: one big cleanup day, and three weeks later it's a mess again. Good: ten minutes at the end of every shift, and a weekly score on the board!
Visual management
Next, visual management. The test is simple: can someone who walks up see, in a few seconds, whether things are normal? There are two kinds. A visual display just informs, like a chart on the wall. A visual control goes further. It tells you what to do, or it even stops a mistake. Floor markings show where carts and racks belong. A painted minimum line on a stock rack says, order more, now. Bad: a whiteboard nobody reads. Good: a signal that triggers an action!
Two visual controls you'll hear about a lot. An andon is a signal light or board that calls for help: green, running. Yellow, I need help. Red, stopped. And a kanban is a card, a bin or a marked space that signals when to make or move more. Remember the two bin system in packing: when one bin runs empty, it goes on the refill shelf, and that empty bin is the signal.
Standard work
Now, standard work. It has three parts. Part one, takt time: the pace the customer needs. Takt time equals available working time, divided by customer demand. Part two, the work sequence: the steps, in the same order every time, with a time for each step. And part three, standard work in process: the small, fixed number of parts that should be waiting at each station. No more, and no less.
Bad: an engineer writes the steps alone, and nobody on the floor ever reads them. Good: the people who do the job help write it, it hangs right at the station, and it changes whenever someone finds a better way. That's the key idea: standard work is the starting point for improvement. Without a standard, there's nothing to improve!
Worked example: the cutting and bending cell
Now, the worked example, back in the cutting and bending cell. Marcus and the crew start with sort. They count one hundred forty items in the cell, and fifty two of them haven't been used in a month. Red tags go on all fifty two, and they move to the holding area for two weeks. Only five get asked for and come back. The other forty seven leave the cell for good! Then, set in order: a shadow board at the bender, the angle gauge right beside it, and the dies on a labeled rack, by tube size.
Shine pays off on day two. Wiping down the bender, Lou spots a slow drip from a hydraulic fitting, and fixes it before it fails. Standardize: a photo of the cell the way it should look, and a one page checklist. Sustain: ten minutes of five S at the end of every shift, and a weekly audit, five points for each S, twenty five in all. The first audit scored nine. By week six, twenty two out of twenty five! Then the visuals: yellow floor lines for the tube carts, a red minimum line on the tube rack, and an andon light on the bender.
Now, standard work for the bender. Takt time first. The cell runs two shifts, with four hundred fifty working minutes each, five days a week. Two, times four hundred fifty, times five, is four thousand five hundred minutes. Customers need about eighteen hundred Harbor chairs a week. Four thousand five hundred divided by eighteen hundred is two point five minutes. That's one hundred fifty seconds. So the bender has to finish one chair's legs at least every one hundred fifty seconds!
Marcus times both shifts, step by step. First shift: pick a tube, ten seconds. Load and clamp, fifteen. Three bends: twenty five, thirty, and twenty five. Unload, ten. Check the angle, fifteen. Onto the cart, ten. That's one hundred forty seconds, under takt. Second shift did the same steps, but walked across the cell to a shared angle gauge, which added twenty five seconds. One hundred sixty five seconds: over takt! Fifteen seconds too slow, times one hundred eighty chairs a shift, is forty five minutes behind, every shift. That's why assembly waited for legs.
The fix: one standard sequence for both shifts, written with Nate and the first shift operator, and posted at the bender, with the angle gauge on the shadow board right there. Standard work in process: one tube in the machine, and one cut tube waiting. Now both shifts run at one hundred forty seconds! And searching dropped from forty minutes a shift to six. That's three hundred forty minutes a week handed back, about one hundred thirty six chairs' worth of time at takt. That answers Rosa's question!
Common mistakes
Common mistakes. One: treating five S as a one time cleanup day. Two: labeling everything, so the labels that matter get lost. Three: visual displays that don't trigger any action. Four: standard work written without the operators, or never updated. Five: setting the pace without knowing the takt time. And six: using five S audits to blame people, instead of fixing the system.
Recap
Let's recap. Five S: sort, set in order, shine, standardize and sustain. Sustain is the hardest, so make it a habit. Visual management shows normal versus not normal at a glance, and the best visuals trigger an action, like an andon light or a kanban. Standard work has three parts: takt time, the work sequence, and standard work in process. And standard work is the baseline for every improvement!
Check yourself
Now, check yourself. A packing cell has three thousand six hundred available minutes a week, and customers need twelve hundred units a week. What is the takt time? A, one third of a minute. B, three minutes. C, thirty minutes. Or D, four thousand eight hundred minutes. Pause the video if you want to think about it.
The answer is B, three minutes. Takt time is available time divided by demand. Three thousand six hundred divided by twelve hundred is three. A flips the formula: demand divided by time gives units per minute, not minutes per unit. C and D don't follow the formula at all. So every station's work has to fit inside three minutes.
Wrap-up
That's five S, visual management and standard work. Questions? Ask Q-Bot right here in the Academy. And one for the road: Q-Bot ran a red tag event on his old jokes. Two weeks in the holding area, and nobody asked for a single one. Except this one, apparently!